The four-stage clearance process

These pages explain the four-stage clearance process that follows licensed asbestos removal work, and how to appoint an independent analyst to carry it out.

The four-stage clearance process

After licensed asbestos removal work has been completed, the work area must be checked to make sure it has been cleaned properly before it can be used again.

The licensed asbestos removal contractor (LARC) first carries out an inspection of the work area. Once they are satisfied that the area has been thoroughly cleaned, the area is formally handed over to an independent analyst for the four-stage clearance process.

The analyst's role is to independently check that the work area is clean and safe for reoccupation or, where appropriate, demolition.

The 4 stages are:

  1. preliminary check of the work area and confirmation that the removal work is complete
  2. thorough visual inspection to check that no visible asbestos debris, dust or waste remains
  3. air testing to check that airborne fibre levels meet the clearance indicator
  4. final assessment after the enclosure or work area has been dismantled

If all 4 stages are completed as satisfactory, the analyst will issue a Certificate for Reoccupation (CfR). This document confirms that the area has successfully passed the four-stage clearance process and is fit for reoccupation, or demolition. A copy of this document should be provided to the person who appointed the analyst, the building owner or occupier (if different), and the LARC.

If there is a failure of any of the four stages, a ‘failed’ certificate should be issued showing which stage failed and giving a reason why.

Further information is available in Chapter 6 of HSG248: The Analysts’ Guide.

Who can appoint an analyst for four-stage clearance

The analyst must be appointed by someone other than the LARC.

This may include, but is not limited to:

  • the building owner
  • the managing agent or landlord
  • the homeowner
  • the builder or installer
  • the client
  • the principal contractor (PC), unless the PC is also the LARC
  • the architect or principal designer
  • another person responsible for managing the project

This helps avoid any potential conflict of interest and supports the independence of the clearance process. If the analyst cannot demonstrate independence, this risks the four-stage clearance being compromised.

How to appoint an analyst

The following is a step-by-step guide to appointing an analyst to complete a four-stage clearance.

1. Confirm that a four-stage clearance is required

A four-stage clearance is only required for licensed asbestos removal work.

Find out more about asbestos work that needs a licensed contractor.

The LARC should advise you that a four-stage clearance is required. You will need to appoint the analyst for the four-stage clearance as early as possible, ideally shortly after appointing the LARC. Early appointment helps ensure availability, allows effective planning between parties and reduces the risk of project delays. When contacting the analyst, you should provide the contact details of the LARC.

2. Choose a UKAS-accredited analyst

A four-stage clearance must be carried out by an independent asbestos analytical organisation that is accredited for this work. The organisation should be accredited to meet the relevant criteria in ISO 17020 and ISO 17025.

In Great Britain, these organisations are accredited by the United Kingdom Accreditation Service (UKAS).

You can find an analyst organisation accredited by UKAS for the four-stage clearance process using the UKAS search tool.

Before appointing an analyst, you should check that:

  • their UKAS accreditation is current
  • they have experience relevant to the planned work

3. Check that the analyst is independent

The analyst must be able to carry out the clearance process impartially, so they can independently verify that the area is safe for reoccupation. To help ensure independence, the law states that the LARC must not appoint the analyst.

Despite this, other ‘shared links’ may exist between the analyst and the LARC that could affect the analyst’s impartiality.

Examples of shared links may include:

  • common ownership (such as where both companies are owned by the same ‘group’)
  • shared directors or managers
  • significant financial or commercial relationships
  • other arrangements that could influence the outcome of the clearance

If shared links exist, the analyst organisation should tell you in writing and demonstrate appropriate measures to address them. In some cases, it may be possible to check this for yourself through a check of their webpage, or Companies House. This will help you to make an informed decision on which analytical organisation to appoint.

Analysts also undertake other site activities that are separate from the four-stage clearance process.

These activities may include:

  • background, reassurance, leak and personal air monitoring
  • witnessing enclosure smoke tests
  • carrying out decontamination unit (DCU) clearance

The legal requirement preventing the LARC from appointing the analyst applies only to the four-stage clearance process and does not prevent the LARC from appointing analysts to undertake these other activities.

4. Make the appointment in writing

To demonstrate ‘appointment’ of the analyst to a regulatory body such as HSE, or auditing body such as UKAS, written documentation should be obtained. This should evidence who appointed the analyst and the four-stage clearance work they were instructed to carry out. Such documentation can be issued by the client or the analytical organisation.

Examples include:

  • a signed contract
  • a purchase order
  • a service agreement
  • an email confirming the appointment
  • an invoice, detailing the work instructed

A verbal agreement is not sufficient.

5. Communication and coordination

Good communication between all parties helps ensure the work is carried out safely, efficiently and with minimal delays.

Having clear lines of communication helps everyone stay informed about:

  • project timescales and key milestones
  • any changes to the planned work
  • resources, equipment and facilities needed to complete the job safely
  • any issues that may affect the project

Once both the LARC and the analyst have been appointed, they should co-operate with each other to exchange information relevant to the project at the earliest opportunity. This may include the ASB5 notification form, plan of work, project timelines and any surveys or sampling undertaken.

Checking the Certificate for Reoccupation

When the Certificate for Reoccupation (CfR) has been issued, you should review it to ensure that the certificate reflects the agreed scope of work.

Check that:

  • all four stages of the clearance have been completed
  • names, addresses and dates are correct
  • photographs are included where appropriate
  • the certificate reflects the work that was completed
  • there are no unexpected caveats such as statements that not all asbestos has been removed
  • where asbestos-containing materials (ACMs) remain, the certificate clearly identifies what remains and where it is located

If you have any concerns about the certificate, contact the analyst and the licensed asbestos removal contractor.

Keep the certificate with your asbestos management records, CDM health and safety file or household records, as appropriate. This document serves as evidence of the asbestos work carried out.