HSE Press Release: E080:04 - 2 July 2004
Two rail companies, Network Rail Infrastructure Limited (NRIL) and AMEC Rail Limited (ARL) were today fined a total of £70,000 at a sentencing hearing at Southwark Crown Court. The case followed an investigation by the Health and Safety Executive (HSE) into the derailment of a passenger train outside West Sutton station in Surrey in 2001. There were no reported injuries and services were reinstated the following day.
On the evening of 9 October 2001, the seventh coach of an eight coach Thameslink passenger train derailed both bogies shortly after leaving West Sutton station at about 18.30 hrs. The train was travelling within permitted line speed, which was 30 mph, and an examination of it did not reveal any faults that could have caused the derailment. At that time Railtrack (now NRIL) was the infrastructure controller and ARL was the infrastructure maintenance controller for the area. HSE's investigations revealed that the cause of the derailment was the condition of the track.
HSE inspector Steve Turner, who investigated the derailment, said: "This was a relatively low speed derailment which happily did not result in any injuries. The investigation revealed that the immediate cause of the derailment was 'gauge spread', that is when the track under the train widens and causes the train wheels to drop in between the rails. Gauge spread can occur over time and it is well known in the rail industry that, if it persists uncorrected, it will result in derailment. Both companies had a duty under the law to ensure that the track was inspected, maintained and repaired; all of which would have picked up this fault and prevented the derailment from happening. Network Rail's new arrangements for managing track maintenance should ensure that a similar incident is less likely to occur."
NRL and ARL each pleaded guilty at earlier hearings to breaching Section 3(1) of the Health and Safety at Work etc Act 1974. NRIL, of Euston Square, London was fined £30,000 and ordered to pay costs to HSE of £12,500. ARL of Stephenson House, Cherry Orchard Road, Croyden, Surrey was fined £40,000 and ordered to pay costs to HSE of £17,500.
1. Section 3 (1) of the HSW Act states, "It shall be the duty of every employer to conduct his undertaking in such a way as to ensure, so far as is reasonably practicable, that persons not in his employment who may be affected thereby are not thereby exposed to risks to their health or safety."
2. The maximum penalty for a single offence under Section 3(1)
of the HSWA in the Crown Court is an unlimited fine.
3. The derailment occurred as the Thameslink train was travelling
through a sharp left curve just outside of West Sutton Station. The
driver first became aware of a problem when he noticed that the
'line light' had disappeared on the control panel, which
meant that the train had lost the traction current, supplying
electricity to the train. Just before the train left the track it
had been travelling at 29mph. The maximum permitted speed was 30mph
due to the curvature of the line. After it became derailed, the
train began to slow due to the gradient of the track and eventually
came to a stop. Records suggest that the train had run without
power for some 340 yards. The train was carrying approximately
seventy passengers. No one was injured and minimal damage was
caused. Investigations showed that the immediate cause of the
accident was the condition of the track, not driver error or the
condition of the train.
4. HMRI began an immediate investigation; enforcement action
followed with the serving an Improvement Notice (IN) on AMEC. The
IN required a number of steps to be taken by 31 January 2002,
specifically 'to improve the arrangements to effectively plan,
organise, control, monitor and review the maintenance of the
permanent way.' The terms of the IN were complied with within
the time specified.
5. The derailment occurred because of a phenomenon known as gauge
spread. Railway track consists of two parallel rails that should be
held at a prescribed distance apart by sleepers. Gauge spread
refers to the distance between the rails increasing as the train
passes over causing the train wheels to drop in between the rails.
It is well known within the railway industry that gauge spread can
cause derailments; indeed it was the single most common cause of
derailments in 2001/2002. The track at West Sutton had been
installed in 1979 by British Rail and comprised rail fastened to
cast iron base plates, known as Pan 8 baseplates, by spring steel
clips. These baseplates were in turn fastened to hardwood timber
sleepers by steel spikes - lock spikes - which were driven down
through a hole in the baseplate and into the timber.
6. Gauge spread occurred because of corrosion failure of the lock
spikes. This was a known and documented failure mode prior to the
derailment. HSE's investigation discovered that the problems at
West Sutton had persisted for some time but had been wrongly
diagnosed. Effective procedures to identify and remedy such faults
ought to have been in place. Since the derailment both Railtrack
and AMEC have taken a number of steps towards improving the systems
for inspection, repair and maintenance of the track in that area.
Railtrack also sent an alert to those engineers elsewhere who had
responsibility for similarly constructed track.
All enquiries from journalists should be directed to the HSE Press Office
Social media
Javascript is required to use HSE website social media functionality.
Follow HSE on Twitter:
Follow @H_S_E