1. A serious incident has occurred which involved the uncontrolled lowering of a crane boom. This notice describes the incident and outlines the actions that should be taken.
2. Many offshore cranes, particularly older cranes, may have hoisting and braking systems that contain 'single line components'; the failure of one such component will result in the failure of the system. This failure will almost always result in the uncontrolled lowering of the boom and/or the load. It is therefore essential to ensure any such components are identified and that the maintenance and inspection philosophy, together with the maintenance and inspection activities undertaken, are sufficiently robust to ensure the continued integrity of these systems.
3. An incident occurred on a Stothert & Pitt OS200 M1 diesel hydraulic pedestal crane that was installed in 1980. The offloading of a supply boat had just commenced and the first load to be lifted comprised of a small 1.8 tonne mini container. As this container was being lifted up and onto the installation a loud bang was heard. The crane boom immediately started to lower in an uncontrolled manner accompanied by screeching and rumbling noises. The falling boom struck two turbine exhausts stacks, damaged a walkway, and came to rest hanging vertically down from the boom hinge pins, with the boom tip in the sea. There were no injuries sustained by the people involved in the lifting operation. However the incident could have resulted in serious injuries or fatalities.
4. The winch units for both the crane main hoist and boom hoist comprised of a hydraulic motor driving a large reduction gearbox. The system of winch braking comprised of a multi-disc brake mounted on the power input side of the gearbox. The output shaft from the gearbox had an external spline that mated to an internal spline on a bossed ring bolted onto the side of the hoist winch drum.
5. Examination of the boom hoist winch revealed that a catastrophic failure had occurred at the splined connection between the gearbox output shaft and the splined boss ring on the winch drum. With the brake mounted on the winch gearbox input shaft, the gearbox and the winch drum to gearbox connection became single line components in the boom hoisting system; the failure of either of these components would result in the uncontrolled lowering of the boom.
6. Failure had occurred through extensive and excessive degradation of the splines, which over a period of time had worn the splines until a point was reached where the remaining contact area was unable to withstand the applied loading.
7. The inspection routine in place at the time of the incident did not include the withdrawal and full visual examination of both male and female splines, therefore the extent of the degradation of the splines was not known.
8. With guidance from the crane manufacturer or a competent person, dutyholders should;
9. The relevant legal requirements are:
10. You can find additional information in the following publications:
11. Any queries relating to this safety notice should be addressed to:
Health and Safety ExecutiveThis guidance is issued by the Health and Safety Executive. Following the guidance is not compulsory and you are free to take other action. But if you do follow the guidance you will normally be doing enough to comply with the law. Health and safety inspectors seek to secure compliance with the law and may refer to this guidance as illustrating good practice
Social media
Javascript is required to use HSE website social media functionality.
Follow HSE on Twitter:
Follow @H_S_E