Office for Nuclear Regulation
An agency of HSE

Hinkley Point A site report - Q3 2009

Hinkley point site stakeholder group quarterly report for 1 July to 30 September 2009


Foreword

This report is issued as part of the Health and Safety Executive's commitment to make information about inspection and regulatory activities relating to the above site available to the public. It is for distribution to members of the Hinkley Point Site Stakeholder Group and covers activities associated with the regulation of safety at Hinkley Point A Decommissioning Site. These reports are distributed quarterly and are also available on the HSE’s web site at http://www.hse.gov.uk/nuclear/llc/index.htm. Site Inspectors of HM Nuclear Installations Inspectorate usually attend Site Stakeholder Group meetings and will respond to any questions raised there by the members of the group.


Inspections

Three site inspection visits were undertaken this quarter:

  • 22, 23rd July 2009
  • 26, 27th August 2009
  • 23rd September 2009 

Inspections were conducted by Teams of NII Inspectors on

  • 22, 23rd July 2009
  • 26, 27th August 2009

Routine matters

Inspections at Site

Inspections at Hinkley Point A are undertaken at site as part of the process for monitoring compliance with:

  1. the conditions attached by HSE/NII to the nuclear site licence;
  2. the Health and Safety at Work etc Act (HSWA) 1974 and
  3. regulations made under the HSWA (for example the Ionising Radiations Regulations 1999 and the Management of Health and Safety at Work Regulations 1999).

This entails monitoring licensee’s actions on the site in relation to incidents, operations, maintenance, projects, modifications, safety case changes and any other matters which may affect safety. The licensee/operators are required to make and implement adequate arrangements under the conditions attached to the licence in order to ensure legal compliance. Inspections seek to judge both the adequacy of these arrangements and their implementation. In this period routine inspections of the site covered:

  • Compliance with “The Regulatory Reform (Fire Safety) Order 2005”
  • Safety documentation
  • Operational Records
  • Examination, Inspection, Maintenance and Testing
  • Leakage and Escape of Radioactive Material and Radioactive Waste

Non-routine matters

Licensees are required to have arrangements to respond to non-routine matters and events. NII inspectors judge the adequacy of the licensee’s/operators response including actions taken to implement any necessary improvements. Matters of particular note considered during the current period include the following.

HMNII has continued to monitor the Licensee’s ongoing investigations into the condition of the three intermediate level waste storage tanks and their secondary containment. Discussions regarding their future will be held in October 2009.


Regulatory activity

Under Health and Safety legislation NII Site Inspectors, and other HSE Inspectors, may issue formal documents to ensure compliance with regulatory requirements. Under nuclear site licence conditions, HSE/NII issues regulatory documents, which either permission an activity or require some form of action to be taken; these are collectively termed Licence Instruments (LI). In addition inspectors may issue enforcement notices to secure improvements to safety.

Licence Instruments

There were no Licence Instruments issued in the period covered by this report.

No enforcement notices were issued during the quarter.


Proposed changes to HSE’s nuclear directorate

Government has decided to restructure HSE’s Nuclear Directorate (ND) to improve further its organisational framework for the sustained delivery of robust, effective and efficient nuclear regulation in the UK. This will place the ND in a better position to meet the anticipated future challenges.

Several factors have come together to make now the right time to restructure ND and create a new independent Nuclear Statutory Corporation (NSC) under the auspices of HSE. These include changing requirements of ageing nuclear power reactors; on-going decommissioning and active management of legacy nuclear plants; assessment of potential new nuclear power stations; growing competitiveness in the global nuclear skills market and the need for improved regulation driven by increased expectation from society for better accountability, transparency and efficiency from public sector bodies.

In addition to this was the government-initiated exercise conducted by Dr Tim Stone which examined the UK’s nuclear safety regulatory regime and identified a number of recommendations for improvement, including the need for structural changes to ND. The Summary Recommendations and the Government’s response were published at the end of January 2009 (available on HSE’s website).

HSE is working on the legislative measure that needs to be in place to create the NSC. These changes will be made through a Legislative Reform Order (LRO) under the Legislative and Regulatory Reform Act 2006.

Informing this, a joint consultation exercise was carried out by DECC and DWP that sought views on the proposed changes. The 12-week consultation period ended on 22 September 2009 and submissions are currently being assessed.

These new arrangements will not change the substance or standards of regulation or compromise the independence of the nuclear regulatory body, and will not affect the decisions it takes or the international obligations the Government requires it to meet.

These reforms are designed to lead to improvements in the transparency, accountability and consistency of regulatory activities, thereby seeking to enhance the confidence of all stakeholders, both duty holders and those with wider interests. The reforms would be expected to offer clear and direct benefits to industry and workers as well as society as a whole, which would benefit from efficient and continued robust and effective regulation of nuclear hazards.

Subject to the outcome of the consultation and Parliamentary approval, and if the Parliamentary timetable permits, the aim is to bring the new body into being during 2010.

An internal change programme is currently operating within ND to ensure that the ND is ready to operate when permitted by Parliamentary approval as a statutory corporation from spring 2010. This programme has identified key areas of action and deliverables, which will sit alongside the current business improvement programme and will ensure that operational business improvements are delivered alongside the set up of the new corporation.

It is important to recognise that this programme does not in anyway compromise the current business activity that is delivered through ND and strives to improve operational effectiveness and stakeholder engagement.


Directgov - Business Link

Updated 17.08.11