HSE banner

Chapelcross Power Station

Site Stakeholder Group

Quarterly report for 1 January 2008 to 31 March 2008

Contents


Foreword

This report is issued as part of the Health and Safety Executive's commitment to make information about inspection and regulatory activities relating to the above site available to the public. It is for distribution to members of the Chapelcross Site Stakeholder Group (SSG) and covers activities associated with the regulation of safety at Chapelcross Power Station. These reports are distributed quarterly and are also available on the HSE’s website at http://www.hse.gov.uk/nuclear/llc/index.htm. Site Inspectors of HM Nuclear Installations Inspectorate normally attend SSG meetings and will be happy to respond to any questions raised there or subsequently by members of the SSG. Any other person wishing to inquire about matters covered by this report should contact the HSE’s, Nuclear Directorate on 0151 951 3484/3290.

Nuclear Directorate
Health and Safety Executive
Redgrave Court
Merton Road
Bootle
Merseyside
L20 7HS

[back to top]


Inspections

The Nuclear Installations Inspectorate (NII) Site Inspector made inspections on the following dates during the quarter: -

  • 15-18, 24, 29-30 January 2008
  • 12-14 February 2008
  • 5-7, 17-18 March 2008

[back to top]


Routine matters

Inspections are undertaken at site as part of the process for monitoring compliance with:

  1. the conditions attached by HSE/NII to the nuclear site licence;
  2. the Health and Safety at Work etc Act (HSWA) 1974 and
  3. regulations made under the HSWA for example the Ionising Radiations Regulations 1999 and the Management of Health and Safety at Work Regulations 1999.

This entails monitoring licensee’s actions on the site in relation to incidents, operations, maintenance, projects, modifications, safety case changes and any other matters which may affect safety. The licensee is required to make and implement adequate arrangements under the conditions attached to the licence in order to ensure legal compliance. Inspections seek to judge both the adequacy of these arrangements and their implementation. In this period routine inspections of Chapelcross covered:

In general the arrangements made and implemented by Chapelcross in response to safety requirements were deemed to be adequate in the areas inspected. However, where improvements were considered necessary, satisfactory commitments to address the issues were made by or are being sought from the licensee, and the site inspector will monitor progress during future visits. Where necessary, formal regulatory enforcement action will be taken to ensure that appropriate remedial measures are implemented to reasonably practicable timescales.

The first quarter of the year is one in which the licensee updates its plan of work. During the quarter the first annual forward look meeting was held between NII and the licensee. This is a formal review of the planned work. The site inspector also took part in the NDA’s Amber Review of the plan of work. A new procedure, known as MCP 99 was implemented by the licensee in 2007. This introduced a new concept known as regulatory milestones to be included in the site’s work plan. The site inspector has agreed an initial set of regulatory milestones and these have been incorporated into the site’s plans.

The site is currently producing its Periodic Safety Review (PSR) and is due to complete it by August 2008. The licensee has started to submit documents to NII in accordance with its programme.

The site is planning to start defuelling in Spring 2008. NII has been monitoring progress towards this and has had several discussions with the licensee to ensure that the site understands the regulatory requirements to ensure that NII can agree to the start of defuelling.

[back to top]


Non-routine matters

Licensees are required to have arrangements to respond to non-routine matters and events. NII inspectors judge the adequacy of the licensee’s response including actions taken to implement any necessary improvements. There are no items of particular note during the current reporting period.

[back to top]


Regulatory activity

Under Health and Safety legislation NII Site Inspectors, and other HSE Inspectors, may issue formal documents to ensure compliance with regulatory requirements. Under nuclear site licence conditions HSE/NII issues regulatory documents, which either permission an activity or requires some form of action to be taken; these are collectively termed Licence Instruments (LI). In addition inspectors may issue enforcement notices to secure improvements to safety.

No LIs were issued to the licensee(s) during the quarter: -

No enforcement notices were issued during the reporting period:

[back to top]