This report is issued as part of the Health and Safety Executive's commitment to make information about inspection and regulatory activities relating to the above site available to the public. It is for distribution to members of the Bradwell Power Station Local Liaison Council (LCLC) and covers activities associated with the regulation of safety at Bradwell Power Station. These reports are distributed quarterly and are also available on the HSE’s web site at http://www.hse.gov.uk/nuclear/llc/index.htm. Site inspectors of HM Nuclear Installations Inspectorate usually attend LCLC meetings and will respond to questions raised there by members of the LCLC. Any other person wishing to enquire about matters covered by this report may contact the HSE’s Nuclear Directorate on 0151-951-3484/3290.
Nuclear Safety Directorate
Health and Safety Executive
Redgrave Court
Merton Road
Bootle
Merseyside
L20 7HS
Bradwell was visited for routine inspections and meetings on two occasions during this quarter. The visits were made on the following dates:
1 – 3 October 2007
10 – 13 December 2007
The main thrust in this period has been concerned with Berkeley’s continued compliance with the requirements of the Nuclear Site Licence. Decommissioning project work has been slowed or deferred following reduced NDA funding.
The site inspector reviewed progress with the cooling pond clean up and ILW sludge removal and storage projects and found that these projects were progressing in a safe and compliant manner.
Nil
The Inspectorate has powers under the Nuclear Site Licence to issue Consents, Approvals and Directions. In addition, the Inspectorate uses Licence Instruments to issue Specifications and Agreements under the conditions attached to the Licence.
No Licence Instruments were issued during the period.