HSE banner

HM Nuclear Installations Inspectorate

BRADWELL NUCLEAR POWER STATION

Quarterly report for 01 APRIL TO 30 JUNE 2005

CONTENTS


FOREWORD

This report is issued as part of the Health and Safety Executive's commitment to make information about inspection and regulatory activities relating to the above site available to the public. It is for distribution to members of the Bradwell Power Station’s Local Community Liaison Council and covers activities associated with the regulation of safety at Bradwell Nuclear Power Station. These reports are distributed quarterly. Site Inspectors of HM Nuclear Installations Inspectorate normally attend LCLC meetings and will respond to any questions raised there or subsequently by members of the LCLC. Any other person wishing to inquire about matters covered by this report should contact the HSE, Nuclear Directorate Information Centre on 0151 - 951 - 4103.

This report will be put onto the HSE Website at www.hse.gov.uk/nuclear/ home under “Local Liaison Committee Reports”.


[back to top]

INSPECTIONS

1. Bradwell was visited for inspections, meetings and investigations on five occasions during this quarter, the inspections containing both a routine element and a reactive element. The visits were made on the following dates:-

In addition to the site inspector’s planned inspection activities, a number of additional activities were carried out. The main thrust in this period has been concerned with Bradwell’s continued compliance with the requirements of the nuclear site licence and continued preparations to enter the decommissioning phase of the station’s lifecycle. Additionally, an inspection of the station’s compliance against the Ionising Radiation Regulations 1999. This was carried out by HMNII specialist inspectors.

[back to top]

ROUTINE MATTERS

2 Routine Inspections

Routine inspections were carried out against the following licence Conditions in this quarter;

The results of these inspections showed Bradwell’s arrangements made under these licence conditions to be generally adequate. Where any minor deficiencies were identified, improvements were agreed with the station.

3 Meetings

Two meetings were held with the station regarding the Near Term Work Plan. The aim of these meetings was to ensure that any regulatory requirements were included in the plan of work covering the next two years.

A meeting of the Bradwell Emergency Planning Consultative Committee was attended as was the thirty seventh meeting of the Bradwell Local Community Liaison Council.


[back to top]

NON-ROUTINE MATTERS

4 Reactive inspections were carried out against the following areas:

Actions were placed on the station to implement any improvements identified during these inspections.


[back to top]

REGULATORY ACTIVITY

Licence Instruments

5 One Licence Instrument was issued during the period agreeing to the placement of PASSPORT work control system into normal operation..

HM Nuclear Installations Inspectorate
St Peter’s House
Stanley Precinct
Bootle
Merseyside
L20 3LZ

07 July 2005