Health and Safety
Executive / Commission
Nuclear
LLC reports
This report is issued as part of the Health and Safety Executive's commitment to make information about inspection and regulatory activities relating to the above site available to the public. It is for distribution to members of the URENCO (Capenhurst) Ltd Local Liaison Committee and covers activities associated with the regulation of safety at Capenhurst. These reports are distributed quarterly. Site Inspectors of HM Nuclear Installations Inspectorate normally attend LLC meetings and will be happy to respond to questions raised there or subsequently by members of the LLC. Any other person wishing to inquire about matters covered by this report should contact the HSE, Nuclear Directorate Information Centre on 0151 951 4103.
The site was visited by NII inspectors on :-
April 27 May 27 June 9 & 22
On 1st April Mr I. Gibson replaced Dr D. Simister as the nominated NII Site Inspector for URENCO Capenhurst Ltd (UCL) Site
Each NII Site Inspector has an inspection programme to inspect compliance of operations on the site with the 36 Nuclear Site Licence Conditions (LCs). During this quarter the new site inspector has concentrated on site familiarisation and other regulatory activities. Licence condition compliance inspections will recommence in the next reporting period.
Various meetings have been held to progress the safety documentation relating to two projects to extend the E23 Plant. Licence instruments have been issued acknowledging receipt of the Pre-Commencement Safety Report (PCSR) and the Safety Commissioning Schedules (SCS) for the E23E extension project and the Preliminary Safety Report (PSR) for the E23G extension project. NII also issued a notification to UCL of the intent to examine the safety documentation for the E23E project prior to the commencement of active commissioning of the facility. NII indicated its intention to assess the criticality arguments within the E23 safety documentation before the issue of an agreement for the commencement of the active commissioning of the E23E plant. Further meetings have been held with UCL to discuss the Safety Commissioning Report covering the E23E inactive commissioning work which will form the basis of the UCL submission seeking permission to commence active commissioning.
A meeting of the URENCO Site Safety Representatives Committee was attended.
A meeting has been held to discuss the safety report for the E22 plant. This was the first in a planned series of meetings between NII to UCL to discuss the scope of, and the methodologies utilised within, safety case documentation produced by UCL in support of the continued operation of existing facilities on site.
The NII site inspector attended the UCL Local Liaison Committee meeting held on 22.6.04.
UCL has announced its proposals for the building of a hex tails deconversion plant on the Capenhurst site to process the "tails" of hex material in stored cylinders into a more stable product suitable for long term storage. Initial discussions between NII and UCL have taken place regarding the UCL proposals.
A visit was undertaken to the current Offsite District Emergency Control Centre facility in Ellesmere Port. The centre is soon to be replaced with new facilities based at the Cheshire Police HQ at Winsford.
Exercise "Commissioner" held at the Cheshire Police HQ at Winsford was witnessed. This exercise was primarily staged to test the working of, and the communication systems at, the new Gold Command/Off Site Emergency Command Centre at Winsford. The exercise provided an opportunity for the key responders to validate the room set up arrangements, test the communication and messaging systems and refresh themselves of the off site emergency plan procedures. Overall the participants considered that the new facilities were very good and although a number of minor improvements were suggested the exercise indicated that the systems and arrangements at the new facility were satisfactory.
The Capenhurst EPCC meeting held on 29.6.04 was attended.
Initial discussions have taken place with UCL on their proposals to take over responsibility from British Nuclear Group for the site electrical distribution system, site fire brigade and the maintenance of the UCL CIDAS system. In addition discussions have taken place regarding the UCL proposal to purchase ex Sports Club Land from BNFL.
Nothing to report this period
Regulatory Actions taken during the quarter -
|
DATE |
DESCRIPTION |
|---|---|
|
None |
The Inspectorate has powers under the licence to issue Consents, Approvals and Directions. In addition, the Inspectorate uses Licence Instruments to issue Specifications, Acknowledgements and Agreements under either the conditions attached to the Licence, or arrangements made by UCL for complying with those conditions. The Consents/Approvals/Directions and Licence Instruments issued during the quarter were -
|
DATE |
TYPE |
No |
DESCRIPTION |
|---|---|---|---|
|
14.5.04 |
Acknowledgement& Notification |
1 |
Pre-Commencement Safety Report for E23E Plant acknowledgement & notification of NII's intent to examine the relevant safety documentation for the project prior to the active commissioning of the plant |
|
14.5.04 |
Acknowledgement |
2 |
Preliminary Safety Report for the E23G Plant |
|
18.6.04 |
Acknowledgement |
3 |
Safety Commissioning Schedules for the E23E Plant |
Published on the HSE web site 31 August 2004