HSE banner

HM Nuclear Installations Inspectorate

BRITISH ENERGY GENERATION LTD - DUNGENESS B POWER STATION

LOCAL COMMUNITY LIAISON COUNCIL REPORTS

Quarterly report for 1 APRIL 2004TO 30 JUNE 2004

CONTENTS


FOREWORD

This report is issued as part of the Health and Safety Executive's commitment to make information about inspection and regulatory activities relating to the above site available to the public. It is for distribution to members of the Dungeness Local Community Liaison Council and covers activities associated with the regulation of safety at Dungeness B Nuclear Power Station. These reports are distributed quarterly and are available on the HSE web site (hse.gov.uk/nuclear/llc/2004/index.htm). Site Inspectors of HM Nuclear Installations Inspectorate (part of the Health and Safety Executive's Nuclear Directorate) attend LCLC meetings and will be happy to respond to any questions raised there by members of the LCLC. Any other person wishing to inquire about matters covered by this report should contact the HSE's Nuclear Directorate Information Centre on 0151 951 4103.


[back to top]

INSPECTIONS

1. The Nuclear Installations Inspectorate (NII) Site Inspector and/or his assistant visited Dungeness 'B' on the following dates during the quarter covered by this report:
27 - 29 April,
11 - 13 May
2 - 3 June
21 - 24 June.

2. Other NII inspectors with specialist technical expertise also visited British Energy establishments during the period so as to support the Site Inspector by performing inspections on the Licensee's nuclear safety case.


[back to top]

ROUTINE MATTERS

3. Compliance Inspections: Routine planned inspections are carried out throughout the year and enable NII to judge whether a licensee is complying with the conditions attached to the Nuclear Site Licence, the Ionising Radiations Regulations, and other relevant statutory provisions on a sampling basis. NII was generally satisfied that Dungeness B had shown satisfactory compliance.

4. Emergency Arrangements: An NII team supported the Site Inspector in witnessing the station's annual "Level 1" demonstration emergency exercise on 23 June. This was judged by NII to provide, in general, an adequate demonstration of the station's emergency arrangements. However, the site inspector is to witness a further demonstration of one particular aspect where further improvements were considered appropriate.


[back to top]

NON-ROUTINE MATTERS

5. Incidents on Site: As part of routine, planned inspections the Site Inspector examined the licensee's arrangements for the recording and investigation of incidents at the power station and, where appropriate, undertook independent investigations to the extent that was warranted by the significance of the incident.

6. Pressure Test Failure: Following preliminary investigation of a pressure test failure on 20 May 2004, the site inspector considered that the arrangements for pneumatic pressure testing at Dungeness B at that time did not ensure, so far as is reasonably practicable, the health and safety at work of British Energy employees and others. The site inspector therefore issued a Prohibition Notice to ban pneumatic pressure testing of plant and equipment at Dungeness B. This applies until the Licensee has ensured that, where pneumatic pressure tests are necessary, they are carried out under a safe system of work. This reinforced the Licensee's own self-imposed suspension of such tests.

Following further specialist investigation, an Improvement Notice was issued (after the reporting period) to require the Licensee to improve the arrangements for ensuring, so far as is reasonably practicable, that suitable and sufficient risk assessments are made and that preventive and protective measures are subject to appropriate control.

7. Change in Staff Structure: British Energy (BE) has announced changes in the station structure in order to improve operational focus and the management of work, and to allow system engineers to focus more effectively on the performance of the systems on the plant. Many of the changes are in response to findings from the activities of WANO (World Association of Nuclear Operators). Further changes are expected as BE rolls out its new Performance Improvement Project. The changes potentially have a beneficial effect on safety on the stations. NII will continue to monitor the implementation of the changes so as to be satisfied that BE is correctly managing nuclear safety related aspects.


[back to top]

REGULATORY ACTIVITY

8. The NII has powers within the standard Nuclear Site Licence Conditions to issue Consents, Approvals and Directions. In addition NII uses Licence Instruments to issue Specifications and Agreements under the conditions attached to the Licence.

In accordance with formal regulatory procedure, NII issued the following document under Site Licence No. 61 during the reporting period:

As discussed in the previous report, these amendments followed HSE's agreement enabling Dungeness B to move to a three year interval between major outages, rather than the previous two year interval. This brings Dungeness B into line with the rest of BE's fleet of Advanced Gas-Cooled Reactors.

9. Under Health and Safety legislation the Site Inspector, or other HSE Inspectors, may issue formal notices in the interest of safety. Following the preliminary investigation described in paragraph 6 a Prohibition Notice was issued:

Prohibition Notice P/2004/nuclear/CET/01 was issued on 9 June 2004 as the site inspector was of the opinion that there had been a failure to carry out a suitable and sufficient risk assessment and failure to make and give effect to appropriate health and safety arrangements to ensure a safe system of work for pneumatic pressure testing of plant and equipment. He was of the opinion that there had been a contravention of Regulations 3(1) and 5(1) of the Management of Health and Safety at Work Regulations 1999 and Sections 2(1) and 3(1) of the Health and Safety at Work etc Act 1974.


Published on the HSE web site 2 November 2004
Back to Local Liaison Committee reports index page