HSE banner

HM Nuclear Installations Inspectorate

UKAEA DOUNREAY

Quarterly report for 1 JULY 2004 - 30 SEPTEMBER 2004

CONTENTS


FOREWORD

The report is issued as part of the Health and Safety Executive's commitment to make information about inspection and regulatory activities relating to the above site available to the public. It is for distribution to members of the Dounreay Local Liaison Committee (LLC) and covers activities associated with the regulation of safety at Dounreay. These reports are distributed quarterly. Site Inspectors of HM Nuclear Installations Inspectorate attend LLC meetings and will be happy to respond to any questions raised there. Any other person wishing to inquire about matters covered in this report should contact the HSE, Nuclear Directorate Information Centre on 0151 - 951 - 4103.


[back to top]

INSPECTIONS

1. The Site Inspectors and Specialist Inspectors visited Dounreay on the following days:

5 - 8 July
27 - 29 July
23 - 27 August
6 - 9 September
21 - 22 September

2. Peter Waller, Head of Coal and Nuclear Liabilities Unit, DTI, visited Dounreay on 6 and 7 July and received presentations on the main technical challenges facing the site, progress on the Dounreay Site Restoration Plan (DSRP), Life Cycle Base Line (LCBL), Near Term Work Plan (NTWP), and on preparations for the Nuclear Decommissioning Authority (NDA). A general site tour was undertaken followed by visits to the Prototype Fast Reactor (PFR), the Dounreay Fast Reactor (DFR), and a number of Fuel Cycle Area (FCA) plants. Mr Waller's observations on the site were generally complimentary and commented that staff are focused on the task of decommissioning and restoring the site.

3. NII Chief Inspector Laurence Williams, and Deputy Chief Inspector Andy Hall, visited Dounreay between 7 and 9 September and plant visits were made to the FCA, PFR and DFR. Mr Williams welcomed the progress that continues to be made on the site restoration He noted that the site is going through a transition period with the setting up of the NDA, however, Dounreay needs to remain focused on the day-to-day management of the site and delivery of the DSRP in a safe manner. He noted that the accelerated LCBL programme may put back a number of key strategic milestones. However, NII considers it important that the hazard reduction programme continues to be delivered to the commitments given in the DSRP.

OTHER DOUNREAY SPECIFIC MEETINGS

4. Meetings were held in Inverness on 20 and 21 July to discuss issues relating to the contaminated land safety case and the site end state. A further meeting was held in Inverness on 29 September to discuss issues associated with the LLW strategy. Technical meetings were held at Risley on 7 September and at Halifax on the 23 September to discuss issues on the DFR ventilation upgrade project.


[back to top]

ROUTINE MATTERS

5. The main thrust of NII activity during the period of this report has been inspection of compliance with Licence Conditions, monitoring of UKAEA investigations of incidents, review of the DSRP and LCBL2, team inspection of quality assurance arrangements, review of a number of safety cases, and the issue of a number of licence instruments for operations and projects.

Routine Inspections


6. The planned routine inspection of the Dounreay site has been reduced this quarter due to NII's involvement in LCBL 2.

Emergency Arrangements
7. This year the national Level 3 exercise was held on 22 September 2004 and was based on a hypothetical incident at Dounreay. The Site Inspector participated at the site, and other NII staff were involved at Inverness and Edinburgh. The exercise scenario was based around a fire in D1203 that developed to the point where there was a release of activity offsite requiring countermeasures. The primary purpose of the exercise was to test the multi-agencies and national response to a civil nuclear emergency in Scotland. There were no significant problems with the site aspects of the exercise. UKAEA is currently producing a report on the exercise that will identify the lessons to be learnt.

Dounreay Site Restoration Plan (DSRP) and Life Cycle Baseline 2 (LCBL2)


8. Two formal triangular meetings were held to review progress on the accelerated LCBL2. Attendees included representatives from UKAEA, NII, Scottish Environment Protection Agency (SEPA), Office for Civil Nuclear Security (OCNS) and DTI's Liabilities Management Unit (LMU). NII commented that an earlier interaction on the proposed accelerated programme would have been preferred. The meetings discussed topics relating to progress on DSRP site activities, update on LCBL2 and NII comments, fuel strategy, prioritisation procedure, and management of change arrangements. UKAEA is to provide more detail on the changes between the current DSRP programme and the accelerated LCBL2 programme so that changes in strategy are more transparent. UKAEA are also to arrange a meeting to discuss the revised fuels strategy. Overall, the meetings went well and were considered useful.

Organisational change

9. UKAEA proposed a significant organisational restructuring at Dounreay to give better focus on delivery of the forward decommissioning programme. The change does not involve an increase or decrease in overall staff numbers. NII examined the proposals in a licence condition 36 submission, and raised a number of issues that were discussed and satisfactorily resolved with UKAEA.

HSE -SEPA 1998 Audit Medium Term Recommendations
10. Overall, UKAEA progress on closing out the 27 medium term recommendations has been less than anticipated. NII requires UKAEA to have a well documented process in place so that it can plan appropriate assessment of the close out requests, and therefore NII asked for additional detail in the close out justifications provided by UKAEA's Independent Inspection Department. UKAEA has addressed this, and subsequently, one of the recommendations has been closed out. UKAEA has provided a programme for close out of the majority of the remaining recommendations by March 2005.

Enhanced Inspection of Quality Assurance (QA) Arrangements

11. Two of NII's specialist QA Inspectors carried out an inspection of Dounreay's QA arrangements. No Requirements were identified specifically for Dounreay, however, the inspection did refer to a corporate finding previously identified at Harwell. Overall, it was considered that Dounreay has made significant improvements to the QA arrangements since the HSE/SEPA Audit in 1998. The inspection provided 3 items of Advice for maintenance and improvement of the effectiveness of the internal QA audit system, although the management and implementation of the audit programme is considered to be of a high standard.

Extension to the current Dounreay Nuclear Licensed Site Boundary

12. Dounreay has applied to enlarge the Nuclear Licensed Site Boundary slightly to encompass the proposed head works for decommissioning of the shaft. The marking of the new site boundary has been delayed by protected species of nesting birds on the foreshore. The other outstanding issue is the signing of the lease to be granted by Crown Estates. This is now almost complete and in anticipation of completion, a provisional date has been set for the signing of the new licence by NII's Chief Inspector. [Note: the new site licence was signed on
25 October 2004]

Lifting the Direction


13. In May 2003 a programme of deliverables for lifting the Direction was agreed with UKAEA Dounreay senior management. UKAEA priority work on producing NTWP04 and LCBL2 and NII's involvement in reviewing thes, resulted in slippage of the programme. However, the programme of deliverables has now been completed, and a formal Close Out meeting has been held. In addition, UKAEA has submitted a Close Out Report to NII, and requested a Consent to remove the restrictions on operations imposed by the Direction and to return FCA operations to normal regulatory control. NII has examined the safety documentation, and as a result, expects to be able to issue a Consent in the very near future. [Note: the Consent was granted on 4 October 2004]

PFR Decommissioning

14. Following the occurrence of a number of incidents at PFR with potentially high consequences early in 2004, UKAEA suspended all operations (except those essential for safety and operation of the Sodium Disposal Plant), and carried out an investigation to identify the problems. The review identified a number of improvements at PFR including, changes to the management structure, control of contractors, clarification of supervisory roles and work control. These are being implemented against a programme for restarting operations. NII believes UKAEA responded appropriately to the occurrence of incidents, nevertheless the situation at PFR continues to be closely monitored by NII.

15. The sodium destruction plant for removing bulk sodium from the PFR reactor is performing well. On completion of the removal of the bulk metal, UKAEA propose to remove the remaining residual layer of sodium by the Water Vapour Nitrogen (WVN) process which is currently under development by UKAEA and the AMMR Alliance. NII has been monitoring this development work closely and, because of the hazardous nature of the process and the unique application, has decided to formally 'call-in' for examination the safety documentation for PFR reactor vessel work.

DFR Decommissioning
16. The validity of the DFR Decommissioning Safety Case (DSC) expired at the end of August 2004. UKAEA raised a modification to extend the DSC until a revised DSC is produced that is linked to the Breeder Fuel Removal project. NII has examined the safety documentation and has accepted UKAEA's proposal.

17. NII's assessment of UKAEA's safety case supporting an agreement for construction of the DFR NaK Disposal Plant continues. A number of specialist technical issues have been raised that are currently being addressed by UKAEA.

Low level Waste (LLW)

18. A meeting was held in Inverness on 29th September to discuss UKAEA Dounreay's strategy for the management of Low Level Waste. The meeting was also attended by LMU and SEPA. UKAEA set out the basis for a long term management strategy covering waste minimisation and segregation, disposal of suitable waste to Drigg (given the granting of an Authorisation from SEPA) and the potential need for a disposal facility at Dounreay. Decisions need to be taken by NDA and Government (DEFRA) before the strategy can be advanced in some areas. NII has agreed that UKAEA should continue to develop this strategy.

Contaminated Land

19. A meeting was held with UKAEA to discuss the contaminated land safety case, and as a result, NII are to monitor the implementation plan and forward improvement programme. The Dounreay site has a number of outside areas that are designated as controlled areas under the IRR's and where fuel particles have been found. NII considers that improvements are required to the containment of these controlled areas, particularly to prevent the intrusion of wildlife, and has recently received details of improved arrangements.

Solid ILW Project
20. The SILW project is a multi-stage, long term project, and UKAEA have agreed to produce an up to date Safety and Environment Overview Report (SEOR). The SEOR will indicate the type and timing of safety, environmental and planning application documentation required for the various sub projects of the overall SILW project. This should assist in eliminating future problems with the coordination of the various activities associated with the project.

D1208 Liquid Effluent Storage and Treatment Plant.

21. Following two inadvertent liquor transfer incidents, UKAEA have carried out a review of the controls associated with liquor transfers in D1208, with the intent of implementing any reasonably practicable improvements. NII considers that the review was comprehensive with regard to hardware controls, but that additional work needs to be done on the review of software and administrative controls. Also, NII has asked UKAEA to provide a programme for implementing the improvements.
UKAEA has already implemented a number of administrative improvements for the control of liquor transfers, including independent verification of diverter valve settings and improved operating instructions.

Vulcan NRTE

22. NII carried out inspections at NRTE VULCAN, during this quarter on the following dates:

6 July
10 - 12 August
7 - 8 September.

Inspection topics covered during the above visits included:
a. The Chief Inspector of the Nuclear Installations Inspectorate visited the site as part of his routine inspection programme. He stated he was content with what he found;
b. Attendance at the Emergency Planning Co-ordinating Committee of the Dounreay Local Liaison Committee which reviewed the arrangements at the site following the Lone Star 04 exercise;
c. Inspecting the site's compliance with the requirements of regulations 7, 8, 14, 21, and 28 of The Ionising Radiations Regulations 1999 (IRRs). No significant issues were raised.
In general the inspections indicated that the site staff are continuing to manage and control the activities in a satisfactory manner, and no significant issues were identified.


[back to top]

NON-ROUTINE MATTERS

Improvement Notices

23. No improvement notices were issued during the period of this report

Incidents on Site


24. No events have occurred during the quarter that met the Ministerial reporting criteria.

25. Incidents reported to NII are included in quarterly reports to the Dounreay LLC and NII gives updates on progress of any significant recommendations from either their own or UKAEA's investigations. UKAEA has a database of incidents and their progress with close out of recommendations is inspected regularly by NII. The overall investigation performance of UKAEA is also considered at the NII - UKAEA annual review of safety.

Dangerous Occurrence at Janetstown


26. On 27 July, a hot gas release occurred from a redundant sodium contaminated vessel during cutting operations into the vessel. An emergency was declared and HSE notified. HSE's Hazardous Installations Directorate (HID) and NII have since been investigating the incident. As a result, it seems likely that HID will serve Improvement Notices on both Alstec and UKAEA. In addition, a previous incident which occurred during Water Vapour Nitrogen operations at Janetstown, is also being investigated. Both events have implications for similar work carried out on the Dounreay site, and until investigations are completed and improvements implemented, similar operations at Dounreay have been embargoed by UKAEA.

REGULATORY ACTIVITY


27. The Inspectorate has powers under the licence to issue Consents, Approvals and Directions. In addition, the Inspectorate uses Licence Instruments to issue Specifications, Acknowledgements, and Agreements under either the conditions attached to the Licence, or arrangements made by UKAEA for complying with those conditions. The following Licence Instruments were issued during the period of this report:
28. A Licence Instrument has been issued Agreeing to the construction of the Dounreay Cementation Plant Import Export Facility. NII does not intend to impose any further regulatory hold points on the subsequent stages of this project.

29. A Licence Instrument has been issued Agreeing to the implementation of UKAEA's proposals for the reorganisation of Dounreay. UKAEA are to provide
2 monthly progress reports to NII, and to submit the findings of their audit on the implementation of the reorganisation.

30. Following a review of the D1215/1218 Laboratories modern standards safety case and the resolution of a number of NII issues, a Licence Instrument has been issued acknowledging the safety case. NII has decided that there is no need for detailed assessment of this particular safety case.


Published on the HSE web site 03 January 2004