HSE banner

HM NUCLEAR INSTALLATIONS INSPECTORATE

UKAEA DOUNREAY

Quarterly report for 1 APRIL 2004 - 30 JUNE 2004

CONTENTS


FOREWORD

The report is issued as part of the Health and Safety Executive's commitment to make information about inspection and regulatory activities relating to the above site available to the public. It is for distribution to members of the Dounreay Local Liaison Committee (LLC) and covers activities associated with the regulation of safety at Dounreay. These reports are distributed quarterly. Site Inspectors of HM Nuclear Installations Inspectorate attend LLC meetings and will be happy to respond to any questions raised there. Any other person wishing to inquire about matters covered in this report should contact the HSE, Nuclear Directorate Information Centre on 0151 - 951 - 4103.


[back to top]

INSPECTIONS

1. The Site Inspectors and Specialist Inspectors visited Dounreay on the following days:
20 - 23 and 27 - 30 April
11 - 14 May
15 - 17 and 22 - 25 June

2. A French regulator delegation visited the site to gather information about radwaste management and decommissioning. The delegation was particularly interested in the PFR Sodium Disposal Plant (SDP) because Electricite de France (EDF) has planned to build two similar facilities for decommissioning French reactors of the same type as PFR. The delegation reported that the visit had been well worthwhile.

OTHER DOUNREAY SPECIFIC MEETINGS

3. A meeting was held in Manchester on 25 May to discuss progress with the Dounreay Site Restoration Plan (DSRP) and Life Cycle Baseline 2 (LCBL2). Technical meetings were held at Risley on 24 and 25 June to discuss issues on the DFR NaK Disposal Plant and on the DFR Breeder Fuel Removal project. A further meeting was held at Risley on 28 June to discuss issues relating to the Dounreay re-organisation.


[back to top]

ROUTINE MATTERS

4. The main thrust of NII activity during the period of this report has been inspection of compliance with Licence Conditions, monitoring of UKAEA investigations of incidents, review of the DSRP and LCBL2, team inspection of records, planning and observation of the annual demonstration emergency exercise, review of a number of safety cases, and the issue of a number of licence instruments for operations and projects.

Routine Inspections

5. Inspection of the Dounreay site has continued largely as planned during the quarter.

Emergency Arrangements

6. The Dounreay Level 1 annual demonstration emergency exercise was held on
13 May 2004. The exercise scenario was based around a 25 tonne fork-lift truck colliding with the corner of a storage tank at D1208, resulting in damage to the building fabric and a release of radioactive material to the environment. The exercise tested the site arrangements for setting up the various incident control centres, mustering of personnel, establishing local containment of the leak, recovery and treatment of casualties, and producing a viable recovery plan.

Overall NII judged the exercise to be a successful demonstration of UKAEA Dounreay's emergency arrangements. The key lesson to be learned relates to improved welfare of sheltering staff in the outlying areas of PFR and DFR.

Dounreay Site Restoration Plan (DSRP) and Life Cycle Baseline 2 (LCBL2)

7. The annual review of the DSRP was attended along with representatives from the Scottish Environment Protection Agency (SEPA), the Office for Civil Nuclear Security (OCNS) and DTI's Liabilities Management Unit (LMU). This was the first formal meeting between UKAEA and these parties to discuss the
acceleration of the DSRP/LCBL programme to 2047. NII commented that an earlier interaction on the proposed accelerated programme would have been preferred. The meeting discussed topics relating to progress on DSRP site activities, update on LCBL2, prioritisation procedure, and site end state. Overall, the meeting went well and was considered useful. A further meeting to discuss in more detail the accelerated DSRP/LCBL programme was set for 8 July 2004.
Organisational change

8. UKAEA is proposing a significant organisational restructuring at Dounreay to give better focus on delivery of the forward decommissioning programme. The change will not involve an increase or decrease in overall staff numbers. NII has no objection in principle to the proposed changes, but has examined the proposals in some detail and raised a number of issues. These have been discussed with UKAEA who have responded to them. These responses were reviewed by NII and there appeared to be no major obstacles to NII agreement to the changes.

HSE -SEPA 1998 Audit Medium Term Recommendations

9. UKAEA has sent NII close out requests for a further 7 recommendations
(making a total of 10 out of 27). NII requires a well documented process in place to so that it can plan appropriate assessment of the close out requests. NII has asked for an additional level of detail in the close out justifications provided by UKAEA's Independent Inspection Department. UKAEA is addressing this, and has submitted one revised close out request that NII is currently reviewing.

Enhanced Inspection of Records

10. NII carried out an inspection at Dounreay as part of a series of inspections of
UKAEA's arrangements for the management of health and safety related records, including operational records. The Inspectors noted that significant improvements have been made since the 1998 Dounreay Audit, and that overall, a generally satisfactory standard of records was found. However a number of
Requirements and Advices were issued to achieve further improvements in some areas.

Extension to the current Dounreay Nuclear Licensed Site Boundary

11. Dounreay has applied to enlarge the Nuclear Licensed Site Boundary slightly to encompass the proposed head works for decommissioning of the shaft. The most significant outstanding issue is the lease to be granted by Crown Estates, and UKAEA has experienced difficulties arranging a meeting with the Crown Estates Office to finalise the wording of the lease. As a result the signing of the new licence by NII's Chief Inspector has been delayed.

Lifting the Direction


12. In May 2003 a programme of deliverables for lifting the Direction was agreed with UKAEA Dounreay senior management. UKAEA priority work on producing NTWP04 and NII's involvement in reviewing it, resulted in slippage of the programme. However, the programme of deliverables is now nearing completion, and a formal Close Out meeting has been held to determine the current timescales for lifting the Direction. UKAEA is now embarking on the final part of the process and is currently producing a Close Out Report for submission to NII. The target date for granting a Consent to lift the Direction is now September 2004.

PFR Decommissioning

13. Following the occurrence of a number of incidents at PFR with potentially high consequences, UKAEA suspended all operations (except those essential for safety and operation of the Sodium Disposal Plant). The root causes were considered to be associated with control of contractors, lack of clarity in supervisory roles and problems in work control. UKAEA carried out a review of the situation at PFR covering safety documentation, work control arrangements, supervisory arrangements, resourcing, interfaces between UKAEA and contractors and delegation of responsibilities. The review identified a number of improvements, including changes to the management structure at PFR, and these are being implemented against a programme for restarting operations. NII believes UKAEA responded appropriately to the occurrence of incidents, nevertheless the situation at PFR will continue to be closely monitored by NII.

DFR Decommissioning

14. UKAEA has now submitted the long awaited revised safety case for the DFR NaK Disposal Plant (NDP). Assessment of this has been treated as important by NII. A meeting has taken place with UKAEA to discuss NII's initial
assessment issues, and at which UKAEA presented details of the DFR management changes, and progress with the DFR Ventilation Upgrade project.

15. A meeting took place with UKAEA to discuss progress on the Breeder Fuel
Removal project at which UKAEA presented updates on the project scope and safety case. A number of key assessment areas were discussed covering seismic criteria, Goliath crane safety case, dose uptake assessment, human factors and security.

Low level Waste (LLW)

16. UKAEA has submitted the final version of the BPEO for long-term disposal of LLW. A triangular meeting was held between the regulators (NII & SEPA), UKAEA and LMU to discuss LLW strategy, progress on the LLW to Drigg application, and the timing and content of the publication of the LLW BPEO and LLW strategy. With regard to the application by UKAEA to send LLW to Drigg, the public consultation by SEPA is complete and SEPA is now in the process of determining the application. SEPA is keeping NII informed of progress as the opening of the Drigg disposal route is a recommendation from the 1998 Dounreay Audit, and is a key part of the site's LLW strategy.

Contaminated Land

17. The contaminated land safety case has been received and a meeting has been arranged on 20 July in Inverness to discuss its contents, implementation plan and forward improvement programme. A linked meeting will also be held to discuss UKAEA's latest proposals for the progression of the strategy for the site end state. This issue has assumed increased importance now that UKAEA is proposing to accelerate the site decommissioning.

FCA Operations

D1208 Liquid Effluent Storage and Treatment Plant.

18. Following NII assessment and acceptance of their proposals, UKAEA has now evaporated and transferred the liquor in one of the cells to one of the Storage Tanks. UKAEA has carried out improvements to prevent any future water ingress into the cell.

19. Following the two inadvertent liquor transfer incidents, UKAEA has implemented improved administrative arrangements for the control of liquor transfers, including independent verification of diverter valve settings. UKAEA has also completed a major review of the hardware, software and administrative controls associated with liquor transfers in D1208, with the intent of implementing any reasonably practicable improvements. A report of the review has been produced and is due to be submitted to NII for assessment.

D2700 Dounreay Cementation Plant (DCP)

20. Following the submission of a LC36 Management of Change proposal, NII agreed to the introduction of 24 hour shift working at DCP. The objective of the change is to enable the cementation of MTR raffinate to be completed earlier than originally programmed.
Vulcan NRTE

21. NII carried out inspections at NRTE VULCAN, during this quarter on the following dates:

27 - 29 April
25 - 27 May.

Inspection topics covered during the above visits included:

a. Attendance at the Dounreay Local Liaison Committee, in conjunction with staff from the Ministry of Defence regulator.
b. Inspecting the site's compliance with the requirements of regulations 19, 21, 25, 28, and 30 of The Ionising Radiations Regulations 1999 (IRRs). No significant issues were raised.
c. Attending and assessing the adequacy of the Off Site emergency arrangements, in conjunction with Ministry of Defence regulator, during the Lone Star 04 exercise. It was considered to be a satisfactory test of the arrangements provided by the Highland Council, as required by the Radiation (Emergency Preparedness and Public Information) Regulations 2001 (REPPIR).
d. Attending the regular meeting of the The Emergency Planning Co-ordinating Sub-Committee of the DLLC, which included a review of the emergency arrangements for the VULCAN and Dounreay sites as a result of the Lone Star 04 Exercise.

In general the inspections indicated that the site staff are continuing to manage and control the activities in a satisfactory manner, and no significant issues were identified.


[back to top]

NON-ROUTINE MATTERS

Improvement Notices

22. No improvement notices were issued during the period of this report Incidents on Site

23. No events have occurred during the quarter that met the Ministerial reporting criteria.

24. Incidents reported to NII are included in quarterly reports to the Dounreay LLC and NII gives updates on progress of any significant recommendations from either their own or UKAEA's investigations. UKAEA has a database of incidents and their progress with close out of recommendations is inspected regularly by NII. The overall investigation performance of UKAEA is also considered at the NII - UKAEA annual review of safety. Following discussions on contaminated land, UKAEA has agreed to formally notify NII of any on-site particle finds.
Investigation into Dose Intake in FCA Plants

25. As a result of a 8.6 mSv intake in 2003, UKAEA has made recommendations to improve bio-assay sampling. The review also looked at means of prevention in the shape of improved engineering controls, supervision and task based risk assessments, and the need to adhere to such measures more closely will be detailed in a site briefing. NII will continue to monitor the impact of the improvements as part of normal regulatory business.

Lost Time Accidents

26. There has been a series of Lost Time Accidents caused predominantly by manual handling issues. These accidents have occurred at D1203, WRACS, D1217, PFR, DFR and D8525 (main stores). UKAEA has reviewed these accidents and concluded that a common key causation factor is that managers and supervisors are not always following the site arrangements for risk assessment in relation to non-nuclear hazards. To rectify the deficiencies UKAEA has formulated an Action Plan that is currently being implemented. NII will monitor the implementation of the Action Plan and continue to monitor UKAEA's performance in this area.


[back to top]

REGULATORY ACTIVITY

27. The Inspectorate has powers under the licence to issue Consents, Approvals and Directions. In addition, the Inspectorate uses Licence Instruments to issue Specifications, Acknowledgements, and Agreements under either the conditions attached to the Licence, or arrangements made by UKAEA for complying with those conditions. The following Consent and Licence Instruments were issued during the period of this report:

28. A Licence Instrument has been issued Agreeing to the Package Movement Safety Case for the Z6016 Flask. This will allow the transfer of ILW from PFR to the D9875 store to commence.

29. A Licence Instrument has been issued Acknowledging receipt of the new facility safety case for D2001. NII does not intend to carry out a detailed assessment of this safety case.

30. A Licence Instrument has been issued to allow UKAEA to begin man entry
decommissioning operations in the Pulsed Column Lab glovebox.


Published on the HSE web site 11 October 2004