HSE banner

HM Nuclear Installations Inspectorate

AWE ALDERMASTON AND BURGHFIELD

LOCAL COMMUNITY LIAISON COMMITTEE REPORT

Quarterly report for 1 July 2004 - 30 September 2004

CONTENTS

FOREWORD

This report is issued as part of the Health and Safety Executive's commitment to make information about inspection and regulatory activities relating to the above sites available to the public. It is for distribution to members of the AWE Local Liaison Committee (LLC) and covers activities associated with the regulation of safety at Aldermaston and Burghfield. These reports are distributed quarterly and are available also from the Internet at http://www.hse.gov.uk/nuclear/index.htm. Site Inspectors of HM Nuclear Installations Inspectorate attend LLC meetings and will be happy to respond to any questions raised there by members. Any other person wishing to enquire about matters covered by this report may contact HSE's Nuclear Directorate Information Centre on 0151-951-4103.

[back to top]

INSPECTIONS

1. A total of 20 NII inspectors visited the Aldermaston and Burghfield sites during the quarter. In addition a group of senior NII inspectors visited Aldermaston as part of a programme involving all nuclear licensees. Also the Deputy Chief Inspector made the second of two familiarization visits to AWE. Inspections were made on the following days:

Aldermaston 1 July
6 - 7 July
13 -16 July
3 - 5 August
17 - 20 August
23 - 26 August
31 August - 2 September
14 - 15 September
21 - 24 September
28 - 30 September
Burghfield 14 July
3 & 5 August
31 August
2 September
9 September
22- 24 September
27 - 30 September

[back to top]

ROUTINE MATTERS

2. Inspections are undertaken for the purpose of monitoring compliance with (i) the conditions attached by HSE to the nuclear site licences, and (ii) other relevant provisions of the Health and Safety at Work etc Act 1974, including the Ionising Radiations Regulations 1999. In this period routine inspections included:

a. Provision and assessment of safety cases and compliance with arrangements made under licence conditions.
b. Management of facility operations and maintenance.
c. Proposals for new plants.
d. Emergency arrangements.
e. Decommissioning of redundant facilities.
f. Waste management.
g. Operating rules, operating instructions, and operational records.
h. Arrangements for the control of modifications to existing plants.
i. Arrangements for the notification, recording, investigation, and reporting of incidents on the sites.

3. Issues arising from these and previous inspections are being pursued. Inspections were made also by HSE's factory inspectors, construction inspector, explosives inspectors, and fire assessor.

[back to top]

NON-ROUTINE MATTERS

Corporate

4. Fire Certificates.
The HSE fire surveyor has visited site and inspected some facilities. Due to security clearance issues he was unable to visit the key production facilities to confirm that the licensee had complied with the 'steps to take' notices. Until recently HSE had not been able to resource this work and AWE has been carrying out their own surveys and making recommendations. Where the HSE surveyor has seen the results of this work he finds it acceptable. New Fire Certificates are to be issued shortly.

5. Quinquennial Review:
NII held a meeting with AWE to discuss their response to issues arising from NII's Quinquennial Review. AWE updated NII on its progress on QQR issues. AWE has made good progress in many areas, namely decommissioning and waste management planning and waste minimisation. There are other areas, such as justification of deferred decommissioning, development of long term waste management strategies and development of safety cases for radioactively contaminated land, which will require further NII consideration.

6. Seismic Categorisation:
AWE is currently in the process of carrying out the Site Seismic Categorisation for both licensed sites. They are in discussions with NII assessors and wish to be able to establish a level of consequence below which they will not have to assess seismic hazard

7. Annual Review Meeting:
The annual safety review meeting between HSE and AWE senior management was held in July. This is an opportunity for AWE to discuss future plans and for HSE to raise current and anticipated future areas of concern or difficulty, where recognition of the issues and a commitment from the AWE directors is sought.

8. Use of Contractors in Decommissioning Work:
AWE has affirmed their intention to draw heavily upon contractors for future decommissioning work. Their aim is to use a specialist "Principal Contractors" who will manage large projects as opposed to placing smaller teams of contractors into facilities where they are managed directly by AWE staff. The licensee have been told that whilst NII has no objection in principle to this approach, AWE will need to demonstrate that they have put in place suitable and sufficient systems to specify the contractor's work and to maintain adequate control and supervision i.e. they meet the intelligent customer/controlling mind requirements.

9. Routine visit of Deputy Chief Inspector:
In line with routine NII practice, Mr R Gray, the Deputy Chief Inspector with responsibility for defence related sites, visited the Aldermaston site. This was his second visit to AWE. On this occasion he toured Aldermaston production facilities, to observe standards of safety and to meet with AWE staff.

Aldermaston

10. Demonstration Emergency Exercise:
The annual demonstration level 1 emergency exercise was held at Aldermaston. This year a criticality scenario was chosen to be tested at AWE. The NII team judged that the demonstration was acceptable, and a number of useful learning points were identified. Unfortunately no off-site emergency services were able to participate. These would have added to the challenge posed by the scenario. However AWE has demonstrated adequate procedures for co-ordinating Local Authority services at previous demonstration exercises, and has an on-site training arrangement with RBFS.

11. Intermediate Level Waste Strategy:
A meeting with AWE set out their strategy for extended storage of intermediate level waste. It involves optimising the use of the stores, changing from 205 litre drums to 500 litre Nirex drums by 2008, and bringing into operation an ILW treatment plant to sort segregate and re-package legacy ILW drums by 2015. NII had no objection in principle to the proposal for reconfiguring storage arrays, provided the licensee can make an adequate safety case; this is expected in November 2004. However it was agreed that the paper did not define a 100-year strategy since it was primarily concerned with ILW store re-configuration issues and did not address waste form issues (conditioning, compatibility of waste form and Nirex 500 litre drum, passivation, etc). NII made clear that unconditioned waste storage over long periods was unlikely to be acceptable.

12. Box Bay Line Decommissioning:
NII met with AWE to discuss their progress in preparing a safety case covering the Box Bay Line and use of plasma arc cutting (PAC) technology. The safety case is being submitted to the NSC in October 2004, and AWE will subsequently seek NII agreement to proceed with decommissioning. Operations covered by the safety case are scheduled to commence around March 2005.

13. NII Inspection Co-ordination Group:
As part of their routine activities the ICG, made up of NII Superintending Inspectors, held a meeting at Aldermaston and visited various decommissioning facilities. These visits to all licensees allow the NII inspection managers to gain familiarity with the different sites and formulate a view with regard to consistency of inspection and future workloads.

Burghfield

14. Demonstration Emergency Exercise:
The annual level 1 demonstration exercise was witnessed by an HSE team of NII and HID inspectors. The MoD Nuclear Weapons Regulator also reviewed the exercise as part of the regulatory team. The licensee was judged to have given a good demonstration of its emergency arrangements and training. Participation of the local authority emergency services allowed a scenario to be set in which the AWE fire service became casualties requiring rescue.

15. Operations on site:
NII has held discussions with AWE on the need to upgrade the infrastructure services on site and refurbishment of the facilities to meet modern standards.

16. NII Nominated Site Inspector:
The NII site inspection duties at Burghfield were handed over to Mr Andrew Lindley at the end of September.

[back to top]

REGULATORY ACTIVITY

19 As part of its regulation under the nuclear site licences NII issues formal regulatory documents, which include Consents, Approvals, Directions, and Licence Instruments .

20 Licence Instrument No. 29, Notification under licence condition 21, for Bays 3 & 4 of A90.

21 No other issues have arisen that have required formal regulatory action.


1 Licence Instruments are issued to acknowledge receipt of specified documents, eg proposals for a new or modified plant; to stipulate whether the Inspectorate intends to examine these documents, or to agree to the start of a particular phase of construction, commissioning, modification, or decommissioning.

Published on the HSE web site 10 January 2005