HSE banner

HM Nuclear Installations Inspectorate

AWE ALDERMASTON AND BURGHFIELD

LOCAL COMMUNITY LIAISON COMMITTEE REPORT

Quarterly report for 1 January - 31 March 2004

CONTENTS

FOREWORD

This report is issued as part of the Health and Safety Executive's commitment to make information about inspection and regulatory activities relating to the above sites available to the public. It is for distribution to members of the AWE Local Liaison Committee (LLC) and covers activities associated with the regulation of safety at Aldermaston and Burghfield. Site Inspectors of HM Nuclear Installations Inspectorate attend LLC meetings and will be happy to respond to any questions raised there by members. Any other person wishing to enquire about matters covered by this report may contact HSE's Nuclear Directorate Information Centre on 0151-951-4103.

[back to top]

INSPECTIONS

1. A total of 19 different NII inspectors visited the Aldermaston and Burghfield sites during the quarter, including a routine visit from Mr L G Williams, HM Chief Inspector of Nuclear Installations. Inspections were made on the following days:

Aldermaston 6 January
13-16 January
20-23 January
27 January
3-5 February
23-27 February
3-5 March
9-11March
23-26 March
Burghfield 21-23 January 3 February
24 February
10 March

[back to top]

ROUTINE MATTERS

2. Inspections are undertaken for the purpose of monitoring compliance with (i) the conditions attached by HSE to the nuclear site licences, and (ii) other relevant provisions of the Health and Safety at Work etc Act 1974, including the Ionising Radiations Regulations 1999. In this period routine inspections included:

a. a. Provision and assessment of safety cases and compliance with arrangements made under licence conditions.
b. b. Management of facility operations and maintenance.
c. Proposals for new plants.
d. Emergency arrangements.
e. Decommissioning of redundant facilities.
f. Waste management.
g. Operating rules, operating instructions, and operational records.
h. Safety mechanisms, devices, and circuits.
i. Arrangements for the control of modifications to existing plants.
j. Arrangements for the notification, recording, investigation, and reporting of incidents on the sites.

3.Issues arising from these and previous inspections are being pursued. Inspections were made also by HSE's factory inspectors, construction inspector and explosives inspectors.

[back to top]

NON-ROUTINE MATTERS

Corporate 4. Radioactive Material Transport:

NII participated in a Quality Assurance audit of radioactive material transport with the Department for Transport inspectors. Whilst working level instructions were found to be reasonable, higher level and corporate instructions were found to be in need of revision to bring them up to modern standards and to meet legislative changes. Safety and security of work at AWE is not compromised by these administrative shortfalls.

5. Familiarisation/ Handover:
A number of inspections have been carried out of AWE facilities, compliance arrangements, and management, for familiarisation and handover to new nuclear site inspectors who have replaced the existing NII site team. The NII site team has returned to the level of 1 superintending inspector, 3 site inspectors and 1 project inspector.

6. Safety Representatives Workshop:


NII inspectors attended a workshop organised by AWE for its safety representatives and contractors' safety representatives. The workshop was well supported by AWE senior management.

Aldermaston

7. Intermediate Level Waste Management:


An ILW management strategy meeting was held at which AWE provided its programme of work for the treatment, storage and assay of all solid ILW on site. This was attended by NII specialist assessors. The conceptual design for the ILW treatment plant, segregation and minimisation of wastes are to be addressed by routine meetings.

8. Hydrodynamics Research Facility:


AWE gave HSE nuclear and explosives inspectors presentations on the hydrodynamics testing capability. These covered possible options, and facility improvements to address limitations and waste minimisation issues with the existing older facilities.

9. Demonstration Emergency Exercise:


The unsatisfactory aspects of the accident response of the 2003 Aldermaston site emergency exercise were exercised again on 25 February 2004. NII judged that there had been sufficient improvement to consider the exercise to be an acceptable demonstration. The participation of Royal Berkshire Fire and Rescue, Royal Berkshire Hospital, and for the February exercise, Royal Berkshire Ambulance Trust, allowed AWE to demonstrate the interface and co-operation with all the rescue, casualty handling, and treatment services.

10. Criticality Team Inspection:


At a meeting on the recommendations from the NII Criticality Team inspection, carried out in February 2002, AWE committed to provide submissions, which should allow NII to close out the remaining issues.

Burghfield

11. Visit by HM Chief Inspector:


Laurence Williams spent a day at Burghfield, where he visited the nuclear licensed site. The Chief Inspector visited a number of facilities and received a range of presentations from the licensee.

[back to top]

REGULATORY ACTIVITY

12. As part of its regulation under the nuclear site licences NII issues formal regulatory documents, which include Consents, Approvals, Directions, and Licence Instruments .

13. Licence Instrument No 26 was an acknowledgement and agreement to start stage 3 of phase 3 decommissioning of a number of glove boxes in building A1.

14. No other issues have arisen that have required formal regulatory action.


Published on the HSE web site 8July 2004