Nuclear Reactors (Environmental Impact Assessment for Decommissioning) Regulations 1999 (as amended) (EIADR)

EIADR regulations

EIADR guidance

Pre-application opinions

When planning to undertake an Environmental Impact Assessment, there is an optional stage where the licensee may request from HSE an opinion on what the environment statement should contain. This is called a Pre-Application Opinion (PAO). In such a case, the licensee must provide information (usually in the form of a scoping report) on which HSE will base its opinion.

Wylfa Nuclear Power Station

HSE has prepared the following Pre-Application Opinion on the content of the Environmental Statement for the decommissioning of Wylfa Nuclear Power Station.

Wylfa Nuclear Power Station pre-application opinion

The Licensee’s pre-application opinion report together with consultees’ comments can be viewed at HSE’s Knowledge Centre at Redgrave Court, Merton Road, Bootle L20 7HS and at the library in HSE’s office in Unit 7 & 8 Edison Court, Ellice Way, Wrexham Technology Park, Wrexham, LL13 7YT: Amlwch Library, Parys Road, Amlwch, LL68 9EA: Holyhead Library, Newry Fields, Holyhead, LL65 1LA: Cemaes Bay Library, Glascoed Road, Cemaes Bay, LL67 0HN: Llangefni Library, Lon-y-Felin, LL77 7RT: Bangor Library, Ffordd Gwynedd, Bangor, Gwynedd, LL57 1DR: Caernarfon Library, Pavillion Road, Caernarfon, Gwynedd, LL55 1AS.

Imperial College Consort Research Reactor

HSE has prepared the following Pre-Application Opinion on the content of the Environmental Statement for the decommissioning of Imperial College Consort Research Reactor

Imperial College Consort Research Reactor pre-application opinion

The Licensee’s pre-application opinion report together with consultees’ comments can be viewed at HSE’s Knowledge Centre at Redgrave Court, Merton Road, Bootle L20 7HS and at the library in HSE’s office in Priestley House, Priestley Road, Basingstoke, Hants RG2 4GW: Ascot Durning Library, High Street, Ascot, Berkshire, SL5 7JE: Sunninghill Library, Reading Room, School Road, Sunninghill, Ascot SL5 7AA: Windsor Library, Bachelors Acre, Windsor, SL4 1ER: Maidenhead Library, St. Ives Road, Maidenhead, SL6 1QU.

Consents issued under EIADR

Oldbury Nuclear Power Station

HSE granted consent to the licensee of Oldbury Nuclear Power Station, Magnox Electric Ltd, to carry out a decommissioning project under the regulations on 18th February 2008. HSE has published a report 'The decision on the application to carry out a decommissioning project at Oldbury Nuclear Power Station under the Nuclear Reactors (Environmental Impact for Decommissioning) Regulations 1999' [769KB]PDF which describes the reasons and considerations for HSE’s decision.

Dungeness A Power Station

HSE granted consent to the licensee of Dungeness A Power Station, Magnox Electric Ltd. to carry out a decommissioning project under the regulations on 13th July 2006. HSE has published a report "The decision on the application to carry out a decommissioning project at Dungeness A power station under the Nuclear Reactors (Environmental Impact Assessment for Decommissioning) Regulations 1999" [350KB]PDF which describes the reasons and considerations for HSE’s decision.

Sizewell A Power Station

HSE granted consent to the licensee of Sizewell A power station, Magnox Electric Ltd. to carry out a decommissioning project under the regulations on 23rd May 2006. HSE has published a report "The decision on the application to carry out a decommissioning project at Sizewell A power station under the Nuclear Reactors (Environmental Impact for Decommissioning) Regulations 1999” [143KB]PDF which describes the reasons and considerations for HSE’s decision.

Chapelcross Nuclear Power Station

HSE granted consent to the licensee of Chapelcross Power Station, Magnox Electric Ltd. to carry out a decommissioning project under the regulations on 26 September 2005. HSE has published a report "The decision on the application to carry out a decommissioning project at Chapelcross Power Station under the Nuclear Reactors (Environmental Impact for Decommissioning) Regulations 1999" [193KB]PDF which describes the reasons and considerations for HSE’s decision.

Calder Hall Nuclear Power Station

HSE granted consent to the licensee of Calder Hall Nuclear Power Station, British Nuclear Group Sellafield Ltd, to carry out a decommissioning project under the regulations on 21 June 2005. HSE has published a report. "The decision on the application to carry out a decommissioning project at Calder Hall Power Station under the Nuclear Reactors (Environmental Impact Assessment for Decommissioning) regulations 1999" [266KB]PDF which describes the reasons and considerations for HSE’s decision.

Hinkley Point A Nuclear Power Station

HSE granted consent to the licensee of Hinkley Point A Nuclear Power Station, Magnox Electric plc, to carry out a decommissioning project under the regulations on 10 July 2003. HSE has published a report, "The decision on the application to carry out a decommissioning project at Hinkley Point A Power Station under the Nuclear Reactors (Environmental Impact Assessment for Decommissioning) Regulations 1999" [135KB]PDF which describes the reasons and considerations for HSE’s decision .

Bradwell Nuclear Power Station

HSE granted consent to the licensee of Bradwell Nuclear Power Station, Magnox Electric plc, to carry out a decommissioning project under the regulations on 5 December 2003. HSE has published a report. "The decision on the application to carry out a decommissioning project at Bradwell Power Station under the Nuclear Reactors (Environmental Impact Assessment for Decommissioning) Regulations 1999" [800KB]PDF which describes the reasons and considerations for HSE’s decision.

Regulation 13 determinations

Regulation 13 of EIADR apply to all decommissioning projects that began after the regulations came into force (19 November 1999) and to existing decommissioning projects that commenced prior to 19 November 1999 that are subject to a change or extension, which may have significant adverse effects on the environment.  In cases where a project is subject to such a change, the licensee must apply to HSE for a determination as to whether an environmental impact assessment is required.

Berkeley Nuclear Power Station

HSE has made a determination under regulation 13 of EIADR that an Environmental Impact Assessment is not required under those regulations for the change to the decommissioning project at Berkeley Nuclear Power Station. HSE has published a report, ‘The Executive’s regulation 13 determination for Berkeley Nuclear Power Station’ [51KB]PDF which describes the main reasons on which the decision is based.

Windscale Piles Decommissioning Project

HSE has made a determination under regulation 13 of EIADR that an Environmental Impact Assessment is not required under those regulations for the change to the Windscale Piles decommissioning project at the Windscale Nuclear Licensed Site. HSE has published a report, ‘The Executive’s regulation 13 determination for the Windscale Piles Decommissioning Project [48KB]PDF which describes the main reasons on which the decision is based.