Inspection
Stage 2: Plan and prepare
For: Inspector/Team leader
Is the scope of the inspection decided?
Establish the scope of the inspection by considering:
- the primary objective(s) and any other aims to be achieved
- the most appropriate sample of evidence needed to make a reliable judgement about level of compliance
- whether any resource constraints will affect the desired scope of the inspection
For: Inspector/Team leader/Administrator/Line Manager
Is the inspection now being planned?
Plan the inspection by considering:
- any previous intervention, accident and enforcement data held on the duty holder
- other D/D contacts with duty holder
- elements of the appropriate rating system
- process risks, safety case/report/licence submissions
- duty holder specific information
- topic guidance from sectors, corporate topic groups, specialists, etc
- when to visit: date(s) and time(s)
- whether the visit should be by appointment or not
- whether to target particular procedures, work processes, equipment, buildings or records
For guidance on this , please see:
in FOD
and in ND
- any relevant liaison arrangements, concordats or memoranda of understanding with other enforcement bodies
For guidance on this, please see:
and in HID:
- MoU between HSE and Environment Agency on the implementation of the Seveso II directive
- MoU between HSE and Scottish Environment Protection Agency on the implementation of the Seveso II directive
and in ND:
Finally:
- plan the agenda for the inspection, including who to interview and when
- identify and secure the people, equipment and other resources required
- ensure staff have the necessary competencies for the role(s) allotted to them
- where appropriate, agree local contact arrangements with employee/safety representatives
- refer and resolve any difficulties through line manager
If it is a team inspection:
- establish the focus and methodology to be used
- decide on the required discipline mix to achieve the objective(s) taking into account any resource constraints
- agree roles
- check for any gaps in the required competencies across the team
- discuss assessment of collected information
- consider availability, travel and accommodation issues, if appropriate
- ensure the team is aware of all potential hazards and precautions to be taken
- determine if any training in site access/emergency procedures is required
Where the relevant details are known in advance:
- record the planned inspection
For: Inspector/Team leader
Are final preparations now required?
Make the following final preparations:
- inform the dutyholder, if appropriate, and also any employee representatives
- ensure any required security clearance/access passes will be available
- consider personal health and safety requirements of inspecting staff and make adequate provision as appropriate
- confirm the availability of any special equipment or PPE needed
- collect relevant documentation identified in step 2.2