The CDM 2007 Regulations apply to most common building, civil engineering and engineering construction work. You must notify HSE of the site if the construction work is expected to either:

  • last longer than 30 days; or
  • involve more than 500 person days of construction work;

HSE should be notified in writing before construction work starts; you can use form F10. Your notification should be sent to the HSE office nearest to the proposed site.

Further information on CDM 2007 is available on HSE's construction section.

Reference

L144 - Managing health and safety in construction (ISBN 9780717662234 - available from HSE Books)