Guidance on ‘as low as reasonably practicable’ (ALARP) decisions in
control of major accident hazards (COMAH)
(SPC/Permissioning/12)
Purpose
The HSE document "Reducing Risks Protecting
People" ( R2P2) was republished as an information document on the 13th
December. The purpose of that document is to address external stakeholders about
HSE`s approach to regulatory decision making. This is accompanied by the so
called "ALARP Suite" comprising three documents; Principles for
Regulators, Good Practice and Design which give guidance to HSE staff. Each part
of HSE will be expected to provide supplementary sector specific guidance to
support implementation. This document aims to give interim guidance specifically
on ALARP demonstrations in the COMAH context and an outline of further work.
This guidance should be read in the context of the policy document (SPC/Permissioning/09)
together with a new generic safety report assessment guide (SRAG) revised in the
light of experience in assessing safety reports (to follow).
Legal background
- The principal health and safety legislation in the uk is the Health and
Safety at Work etc. Act 1974 (HSW Act). It requires risks to employees, and
others, to be reduced ‘so far as is reasonably practicable’ (SFAIRP).
The meaning of SFAIRP has been the subject of legal judgment in the UK
courts (Edwards v National Coal Board). Risk assessments are also required
by The Management of Health and Safety at Work Regulations, Reg 3.
- Regulation 4 of the COMAH Regulations requires Operators to "take all
measures necessary (AMN) to prevent major accidents". This is
interpreted as the equivalent of reducing risks "as low as reasonably
practicable" (ALARP). In terms of what they require of duty-holders,
HSE considers that duties to ensure health and safety so far as is
reasonably practicable ("SFAIRP") and duties to reduce risks as
low as is reasonably practicable ("ALARP") call for the same set
of tests to be applied.
- The demonstration that AMN have been taken to reduce risks ALARP for top
tier COMAH sites should form part of the Safety Report as required by
regulations 7 and 8 of the COMAH Regulations. The required level of detail
is specified in Schedule 4 to the Regulations.
Existing guidance
- HSE has produced a suite of guidance documents concerning ALARP. These are
designed to give high level principles which separate parts of HSE can then
use to promulgate sector specific advice. The documents are:
- The HSE discussion document "Reducing
Risks, Protecting People - HSE's decision making process" (R2P2)
sets out, in more detail, HSE’s approach to making decisions about SFAIRP
and ALARP. It is a further development of ideas previously promulgated in
HSE’s Tolerability of Risks from Nuclear Power Stations (TOR) document
(1992) which defined three regions of risk, delineated by an unacceptable
region and a broadly acceptable region; the region in between defining a
region of tolerable risk, but only when those risks are ALARP.
- R2P2 makes some important statements of
principle:
Principle 1
"HSE starts with the expectation that suitable controls must be in
place to address all significant hazards and that those controls, as a minimum,
must implement authoritative good practice irrespective of situation based risk
estimates".
Principle 2
"The zone between the unacceptable and broadly acceptable regions is
the tolerable region. Risks in that region are typical of the risks from
activities that people are prepared to tolerate in order to secure benefits in
the expectation that
the nature and level of the risks are properly assessed and the results
used properly to determine control measures;
the residual risks are not unduly high and kept as low as reasonably
practicable (the ALARP principle); and .
the risks are periodically reviewed to ensure that they still meet the
ALARP criteria, for example, by ascertaining whether further or new controls
need to be introduced to take into account changes over time, such as new
knowledge about the risk or the availability of new techniques for reducing or
eliminating risks."
Principle 3
"both the level of individual risks and the societal concerns
engendered by the activity or process must be taken into account when deciding
whether a risk is acceptable, tolerable or broadly acceptable’ and ‘hazards
that give rise to …. individual risks also give rise to societal concerns and
the latter often play a far greater role in deciding whether risk is
unacceptable or not".
- For high hazard sites, societal risks/concerns are normally much more
relevant than individual risks, but individual risk must still be addressed.
Although R2P2 gives clear guidance on
individual risk criteria, it gives only limited guidance on criterion values
for societal risks (50 fatalities at less than 1 in 5000 per annum, point on
the boundary between the ALARP band and intolerable band).
- ALARP guidance specific to the COMAH regulations is provided in:
ALARP demonstration requirements
- HID will consider AMN to be in place for people when S2 and S3 risks
are demonstrated to be ALARP and that demonstration has been accepted and
verified. AMN must be in place for each MA. HID’s assessment will be
proportionate, particularly for safety critical events.
- The tools used in Safety Reports to demonstrate ALARP will vary depending
on the level of risk. However, the measures in place to prevent or limit
major accidents should be described in the safety report and be at least to
'relevant good practice’. The assessor will need to focus on these
measures to be satisfied they do represent good practice etc. HID will
regard relevant good practice to have met the AMN requirement when:
- the societal risks can be shown (subject to uncertainty) to be broadly
acceptable, e.g. by use of an approximate risk integral [1]
(ARI) or other societal risk methodology; and
- no group, or individual, is subject to relatively high individual risks
that are not ALARP.
- HID regard good practice as being subject to the process of continuous
improvement and will encourage industry to keep it up-to-date as
technology advances and societal concern about MAHs varies.
- Having been satisfied that the measures in place represent relevant good
practice, the residual risks will be in one of the following category bands:
Intolerable risk
Clearly, if the risk is in this region (whether for individual or societal
risk) then ALARP cannot be demonstrated and action must be taken to reduce the
risk irrespective of cost.
"Tolerable if ALARP" Risk
If the risks fall in this region then a case specific ALARP demonstration is
required. The extent of the demonstration should be proportionate to the level
of risk.
Broadly acceptable risk
If the risk has been shown to be in this region, then the ALARP demonstration
may be based on adherence to codes, standards and established good practice.
However, these must be shown to be up-to-date and relevant to the operations in
question.
This is shown diagrammatically in Figure 1.

- A case specific ALARP demonstration is essentially a simple concept which
can be satisfied by the Operator answering the following fundamental
questions in relation to the identified MAH scenarios: [2]
Q1 "What more can I do to reduce the risks";
The answers to this question are qualitative in nature. The operator should
look systematically at the risks from his operations and draw up, in a
proportionate way, a list of measures which could be implemented to reduce those
risks. Only in a minority of circumstances will there be nothing further that
the Operator could do without shutting the plant down completely. Operational
Policy Unit (OPU)4 have initiated research work to produce a database of risk
reduction measure to assist assessors in determining if anything more might be
done. However, the need to act is determined by answering the second question.
Q2 "Why have I not done it"
The answer to this question may be qualitative or quantitative in nature
depending on the predicted level of risk prior to the implementation of those
identified further measures. Whichever way the question is answered, if the
measure is "prima facie reasonable", based on engineering
considerations, and it cannot be shown that the cost of the measure is grossly
disproportionate to the benefit to be gained, then the Operator is duty
bound to implement that measure.
- Inspectors will require guidance on determining whether an Operators
arguments on gross disproportion are valid (see para 48
and Annex).
Proportionality decisions
- Proportionality must be considered for at least 2 aspects of Safety Report
assessment; the rigor (or robustness) of the risk assessment used and the
depth of the ALARM demonstration. It may also be appropriate when
considering the appropriate level of gross disproportion, a specific element
of the overall ALARP demonstration (see para 48).
Proportionate risk assessment
- The existing HSE published guidance states ‘the depth of the analysis in
the operator's risk assessment should be proportionate to (a) the scale and
nature of the major accident hazards (MAHs) presented by the establishment
and the installations and activities on it, and (b) the risks posed to
neighbouring populations and the environment i.e. the assessment has to be
site specific.’ The risks referred to here include both individual and
societal risk.
- The depth of analysis that needs to be present depends on the level of
risk predicted before the identified additional measures are applied. The
nearer the risk is to the intolerable boundary (i.e. the greater the
proportionality), the greater the depth of analysis. There are various kinds
of risk assessment that may be used depending on proportionality. These
range from Qualitative at the lowest level, through Semi Quantitative up to
Quantitative at the highest level.
Risk criteria
- Criteria for the boundaries of tolerability of risk have been developed
for Individual risk, but there are no adopted UK criteria for Societal Risk
other than that in R2P2.
Individual risks
- Where individual risks have been satisfactorily quantified in a Safety
Report , then it is possible to compare the value with the individual risk
criteria published in R2P2. The risk
criteria are risks of death (to be distinguished from other types of risk
such as risk of dangerous dose used in HSE`s land use planning approach).
These are illustrated in Figure 2.

- A diagram similar to Figure 2 can be constructed for societal risks but
with appropriate criteria. These criteria will be discussed later (see para
32, Figure 4).
Societal risks
- Societal risk is the relationship between frequency of an event and the
number of people affected. Societal concern includes (together with the
societal risk) other aspects of societies reaction to that event. These may
be less amenable to numerical representation and include such things as
public outcry, political reaction, loss of confidence in the regulator, etc.
As such, societal risk may be seen as a subset of societal concern.
Alternatively, societal concern may be regarded as all the factors that go
into making a judgement as to whether the costs of further risk reduction
are grossly disproportionate.
- One way to determine proportionality for societal risks is to use the
maximum potential fatalities (Nmax). This value must be estimated as part of
the ‘assessment of the extent and severity of the consequences of
identified major accidents’ which is mandatory minimum information. The
value of Nmax can be combined with the frequency of the event causing Nmax (fNmax)
to determine an indicator of societal risk levels. This can be compared with
suitably determined criteria. Methodology and Standards Development Unit (MSDU)
have developed a societal risk methodology (ARICOMAH) to help Inspectors
assess this aspect of safety reports. The methodology will be described
later (see Section 6).
Risk assessment rigor
- The level of risk (either individual or societal) can be used to determine
the type of risk assessment an assessor would expect to see in a Safety
Report as illustrated in Figure 3

- The definitions of Q, SQ, QRA, etc. are based upon definitions of types of
risk assessments set down in HSG 190 and developed further in the Generic
SRAG (with intermediate levels where appropriate), but in essence the type
of risk assessment which is appropriate in a demonstration will vary
gradually in depth and level of quantification from qualitative (Q) at one
end to full quantified risk assessment (QRA) at the other.
Risk Matrices & their use in COMAH Safety Reports
- Risk assessment techniques range from a simple qualitative approach to a
detailed quantitative assessment. Fully quantified risk assessments are very
costly and time consuming exercises, and there is within the chemical
industry resistance to adopt such practices. One method which may help to
bridge the gap between purely qualitative and full QRA approaches is to use
a risk matrix. This type of approach has been widely used by many operators
in their COMAH safety reports.
- Risk is interpreted as the combination of consequence (severity) and
likelihood (frequency). Both these are minimum requirements of COMAH safety
reports (Schedule 4 Part 2). A risk matrix enables this combination to be
represented graphically. It is a reasonably quick and easy method to
visualise the spread of risk and consequently is commonly used during (or
after) hazard identification studies (such as a HAZOP), to screen hazards or
to conduct a simple risk analysis. The main advantage of the matrix is its
easy representation of different risk levels, and the avoidance of more time
consuming quantitative analysis where this is not justified.
- The basis for the risk estimate is usually qualitative, although it can be
quantitative (for either the consequences or the frequencies or both). The
matrix, as illustrated below, typically comprises a square divided into a
number of boxes, with each box representing a different underlying risk
level.
Risk Matrix (Illustrative)
|
Likely > 10-2
|
Intolerable
|
Intolerable
|
Intolerable
|
Intolerable
|
Intolerable
|
|
Unlikely 10-4 - 10-2
|
Tolerable (Intolerable if Fatality >10-3)
|
Tolerable (Intolerable if Fatality >10-3)
|
Intolerable
|
Intolerable
|
Intolerable
|
|
Very Unlikely 10-6 - 10-4
|
Tolerable
|
Tolerable
|
Tolerable
|
Tolerable
|
Intolerable
|
|
Remote 10-8 - 10-6
|
Broadly Acceptable
|
Broadly Acceptable
|
Tolerable
|
Tolerable
|
Tolerable
|
| |
Single Fatality
|
2-10 Fatalities
|
11-50 Fatalities
|
50-100 Fatalities
|
100+ Fatalities
|
- Further advice on this is attached to the SPC on Lines to Take (SPC/Permissioning/11
– COMAH Safety Reports: Technical Policy Lines to Take for Predictive
Assessors) and a similar document appears in the September edition of The
Chemical Engineer [3]. Whilst that
article is authored by Mark Middleton of DNV, the risk matrices part is
based on work commissioned from DNV by HID OPU and has been disseminated to
Land Division's Field Discipline Team. The article also had some editorial
input from OPU and MSDU.
- Another approach suggested by MSDU is to use a non cumulative fn
(frequency, numbers of people killed) plot to visualise the spread of risk
and guide the proportionality to be used for examining risk reduction
options. Further advice on this should be sought from MSDU.
Proportionate ALARP demonstration
- Proportionality is also relevant to the determination of the depth of
analysis used to demonstrate ALARP.
- With reference to Figure 1, the higher the risk is
within the "tolerable if ALARP" region, the greater will be the
depth of demonstration required (e.g. Greater effort needed to determine
potential risk reduction measures) to show that those risks are ALARP.
A tool for combined ALARP determination using Societal Risk (ARICOMAH)
- However much care is taken in designing, constructing
and operating an installation that uses large quantities of dangerous
chemical substances there remains a possibility that a release will occur
resulting in a multi-fatality accident. The best available technology for
studying this "societal risk" is full scope application of
quantitative risk assessment (QRA). However, the technique is time-consuming
and requires a high level of technical capability. Given the realities of
limited time and money, Operators have been reluctant to embark on such a
course in preparing COMAH Safety Reports. Recognising this, MSDU have
developed a methodology (ARICOMAH) that can be applied by assessors to
provide a rough but rapid indication of the magnitude of societal risks [4].
This can be used to come to a view on:-
- the type of risk assessment required;
- the extent of the ALARP demonstration; and
- the level of gross disproportion to be assumed when deciding if a risk
reduction measure is "reasonable".
The tool can be used to make judgements on proportionality for i), ii) and
iii).
- Within the methodology a parameter is defined, suitable for comparison
with criteria, and its value calculated. Evaluation of the parameter by hand
is not practicable so a simple software routine has been developed by MSDU.
The inputs to the model are:
- the highest number of fatalities from a single event (Nmax);
- the frequency of that event(fNmax) expressed in chances per million per
year (cpm); and
- a judgement as to whether the event is directional in nature (e.g. toxic
cloud dispersing with the prevailing wind) or not (e.g. a BLEVE).
- If the calculated value is sufficiently low then HSE might be satisfied
that nothing further is required. For higher values, a more comprehensive
site-specific risk assessment and ALARP demonstration may be deemed
necessary.
- A value for the boundary between the intolerable region and the
"tolerable if ALARP" region on the societal risk equivalent of
Figures 2 and 3 can be determined from the societal risk criteria given at
paragraph 136 of R2P2 if this value is assumed to be a point on an F-N curve
with a slope of -1 (as confirmed by RAPU). This ARICOMAH value is calculated
to be approximately 500,000 see Figure 4 below).
- The boundary between the broadly acceptable region and the "tolerable
if ALARP" region is assumed to be two orders of magnitude below the
intolerable boundary. This ARICOMAH value is calculated to be approximately
2,000 (see Figure 4 below).

- Inspectors should be aware that there may be considerable uncertainties
attached to the ARICOMAH inputs and that the values calculated
should be used to give an indication of the level of societal risk rather
than an absolute value.
Decisions by assessment teams that ALARP has been demonstrated
- In relation to COMAH Safety reports, the decision as to whether ALARP has
been demonstrated will be one for the whole Assessment Team to make
collectively, taking account of the application of individual inspectorial
discretion. Inputs to that decision will include:
- The level of risk (both on and off site, individual and societal);
- The arguments used in making the demonstrations in the Safety Report;
- If there are further risk reduction measures that the Operator has not
considered; and
- Other factors that the Team feel are relevant.
Differences of opinion will arise and these should be resolved at the
appropriate management level.
Work in progress
- Whilst the basic framework and tools for determining the suitability of
ALARP demonstrations are in place, there are a number of areas where
guidance for assessors is still being developed. These are described below.
Risk Reduction Measures (RRMs) database
- In order to assist Assessors in determining if Operators have considered
all the relevant RRMs, a database is being developed by HSL/Amey Vectra
which draws together unstructured, paper based lists of measures which have
been considered within HSE in the past, together with measures discussed in
the open literature or research reports written for HSE.
Calculation of Nmax
- The dimensions of the worst-case accident footprint are calculated using
the appropriate fire, explosion or toxic gas dispersion model, the endpoint
being that thermal dose, overpressure or toxic dose that corresponds to the
LD50. Allowance is made for attenuation of toxic dose for an indoor
population when appropriate (e.g. a residential population at night). The
number of survivors within the contour is assumed to equal the number of
fatalities outside the contour. This will be cautious in most cases.
- The information on Nmax should be provided by the occupier in his
`severity and extent` calculations. However, not all Safety Reports are
providing this information and a decision will have to be made whether to
await this or for predictive assessors to estimate the value of Nmax.
Options for this are being explored but, in principle, if the safety report
does not contain the required information then it ought to be rejected at
the Early Predictive Screen stage.
- Other options include providing hazard ranges in graphical form, provision
of software for hazard range calculation, or asking Health and Safety
Laboratories to make estimates on the assessors behalf. Inspectors should be
aware that there may be uncertainty in the value of Nmax.
Calculation of fNmax
- The frequency of the worst-case release is then set using either the
generic value normally used in MSDU’s QRA methodology RISK AT [9] or a
site-specific value if sufficient information is available to satisfy HSE
that that value is warranted. Where the consequence is unidirectional
additional multipliers are then introduced, making the frequency of the
worst-case accident equal to:-
Failure frequency (RISKAT or site-specific)
* conditional plume probability
* weather and wind speed
probability
* wind
rose bias factor
* population distribution factor.
- Guidance on these parameters is given in the Hirst and Carter paper.
Information to enable the appropriate value of each parameter to be
determined should be included in the Safety Report. Again, Inspectors should
be aware that there may be uncertainty in the value of fNmax.
Distribution of ARICOMAH Software
- The most appropriate method to enable assessors to access this small piece
of software has yet to be decided.
CBA guidance
- Guidance for Assessors on Cost Benefit Analysis is being developed. Annex
2 provides some examples of how CBA can be used in a relatively simple
way to make decisions on reasonable practicability.
Guidance on gross disproportion
- All RRMs will involve a cost to the Operator.
Equally, an RRM is intended to reduce risk from an operation and this
reduction will bring about a benefit (reduction in lives saved, etc.) which
can be expressed in monetary terms. The ratio of the costs to the benefits
can be described as a "proportion factor" (PF). Generally, the
value of avoiding a statistical fatality is approximately £1m. It should
also be noted, however, that the benefits might also include the avoidance
of such thing as environmental cleanup costs, increased insurance premiums,
loss of asset value, the costs of increased regulatory interference, etc.
- If this PF is greater than some defined value, then the costs can be said
to be grossly disproportionate to the benefits and the RRM would not be
"reasonably practicable". The difficulty lies in defining what
this limiting value of PF should be.
- It is assumed that, within the "tolerable if ALARP" region, the
minimum value of PF will be 1 since values below 1 imply a bias against
safety. It is further assumed that the value of PF will increase in some way
as risk increases. That is to say, the operator would be expected to pay
more to reduce risk by a given amount if the initial level of risk is close
to the intolerable limit than if the risk were just above the broadly
acceptable limit (Principles and Guidelines
document, para.25). In the intolerable region, RRMs must be implemented
almost regardless of cost, implying an very high, or infinite PF (though it
is recognised that CBAs and gross disproportion are not applicable in this
region).
- The difficulty lies in defining the upper limit of PF and the way PF
increases with risk. An upper value for PF of 10 has been suggested but the
way PF changes with risk is still unclear. However, the basic principle is
shown in Figure 5.

- Within the Broadly Acceptable region, providing DH’s comply with
relevant good practice, additional RRMs are assumed to be not reasonably
practicable implying a PF of zero. However, if there are obvious and cheap
measures that could be taken they should at least be considered. Some
guidance on proportion factors is given in Annex 1 to
this paper.
- Case specific ALARP demonstrations should only be based on the societal
risk from a site and not the societal concerns (Principles
and Guidelines document, para. 34).
- HID believe that there may be a number of site specific issues which
should be taken into account by the assessment team. These include the
presence of hospitals or significant numbers of children or the elderly.
Here, difficulties in organising and evacuating these groups means there is
an additional risk factor to be taken into account. Also, due to factors
such as physiology, state of health, etc., people in these groups may also
be more vulnerable to the effects of the hazard. The assessment team may
decide that the presence of these groups calls for an increase in the
societal risk based gross disproportion factor (i.e. an increase in PF)
Review of Relevant Good Practice (RGP) for HID sites
- HID need a view on whether the codes standards and good practice currently
used by Operators (e.g. LPGA Cop1, HS(G) 28, etc.) can be considered as
relevant and up to date. Work has begun but this may only indicate the scale
of the problem in a few selected cases (e.g. LPG). A more thorough review
may be a longer term goal and would require the significant involvement of
Industry bodies.
Guidance on Lines of Defence analysis
- Arguments that risks have been reduced ALARP based upon `strength in
depth` concepts such as Layers of Protection (LOPA) or `Lines of Defence`
may be used by companies in making demonstrations that all measures
necessary have been taken. Some research is being undertaken with Vectra/HSL
with a view to guidance.
Demonstration frameworks
Flowsheet approach
- HSE choose not to be prescriptive on how demonstrations that all necessary
measures have been taken should be made, but one way of approaching this is
set down in the attached flow sheet at Fig 6. This
method assumes that the risks are not intolerable.
Stepwise approach
- Alternatively we have found that some Duty Holders have used the following
stepwise approach. This approach assumes that the risks have been shown to
be in the "tolerable if ALARP" region and that a case specific
ALARP demonstration is required:
- Identify controlled substances, their inventories and locations. Show
the local environment including on and offsite populations that may be
affected and other hazardous installations (including those at designated
domino effect sites) that might be affected by major accidents or be
initiators of a major accident. Show that the required measures are, at
least, to current authoritative good practice.
- Identify all major accidents and develop a qualitative view on the
significance of each one. In the light of the view on the significance of
all the identified major accidents, choose a representative subset for
detailed consideration.
- Refine the prediction of the hazard range and its likelihood, for each
event in the chosen representative subset.
- Refine the prediction of the consequences, for each event in the chosen
subset, including estimates of the number of fatalities, major and minor
injuries to man and damage to the environment, and develop a view on the
extent of lesser harms such as major and minor injuries to persons.
- Show the consequences and the likelihood, for each event in the chosen
subset, on a suitable matrix or fN plot (with suitable error bands).
- Divide the area of the matrix (or plot) into 3 bands (broadly acceptable
risk, tolerable if ALARP, intolerable risk) and calibrate these bands
against criteria. Suitable numerical criteria for individual risk are set
down in R2P2.
- For intolerable risks immediate action should be taken to reduce risks.
For those events in the broadly acceptable region a comparison with
relevant standards should be appropriate. For those events in the TIFALARP
region look at the major accidents in a particular consequence band and
select the ones with the highest frequencies.
- For these, determine what additional risk reduction measures, beyond
relevant good practice standards, (software as well as hardware) may be
implemented.
- Implement these measures unless a reasoned argument is presented showing
the costs to implement this scheme are grossly disproportionate. Arguments
based upon `strength in depth` concepts such as Layers of Protection (LOPA)
or `Lines of Defence` may be used when these have been developed
sufficiently. Where the risks have been assessed as high, the use of
formal cost benefit analysis may be required to test the cost-benefit
balance for the prospective remedial measures.
- Revisit step 7 for lesser consequences and continue until proportional
demonstrations are made.
Further information
For further information, please contact CD2.4, St Anne’s House, Bootle
(0151 951 4062).
(Exemption 13 applies to section A1.3 of Annex 1: Commercially confidential
information)
Figure 6: ALARP demonstration flow sheet
ANNEX 1: guidance on proportion factors
A1.1 Work by RAPU and ESAU
Le Guen, Hallett and Golob produced a paper on the "Value of preventing
a Fatality" which was circulated to HSE Board members and presented to the
Risk Assessment Liaison Group (RALG) (RALG/Sep00/03). That paper discussed the
ratio of the cost of preventing a fatality (CPF) to the value of preventing a
fatality (VPF). The starting point for VPF was taken to be the DETR figure of
approx. £1m used in new road schemes. Other values of VPF were then described.
These were 2 x DETR for deaths from cancer and 3 x DETR for some aspects of
railway safety. It is HID OPU4’s contention that the values of 2 and 3
represent proportion factors (PF) similar to those described in Section 8F
earlier.
The paper also examined the implied ratios of CPF to VPF in a number of CBAs
(and RIAs) carried out prior to the implementation of a number of sets of
regulations. Part of that table is reproduced below. To this has been added a
column reflecting a estimate for the number of people who may be affected in any
given incident controlled by the relevant Regulations (taken from, or implied
by, the text in the Board paper):-
|
Regulations
|
Year
|
CPF/VPF (or PF)
|
Nmax?
|
|
Control of Legionellosis Regs. And ACOP
|
1990
|
2.6 - 8.5
|
6
|
|
Gas Safety (Management) Regs.
|
1996
|
1.4 - 1.7
|
1 to 2
|
|
Adventure Activities Licensing
|
1996
|
5.4
|
>2?
|
|
Confined Spaces
|
1996
|
1.0 - 2.2
|
1 to 2
|
|
Railway Safety
|
1999
|
7.1 - 10.5
|
Approx. 30?
(Ladbroke Grove)
|
Whilst in no way definitive, the above data could be seen to show an increase
in PF with increase in numbers affected.
A1.2 DNV Offshore Guidance
The document "A Guide to Quantitative Risk Assessment for Offshore
Installations" prepared by DNV includes some guidance on gross
disproportion and the value of statistical fatalities.
Section 25.8.3 of that document states:-
"The necessary degree of disproportion is generally considered to be low
near the negligible criterion, rising to in effect infinity at the maximum
tolerable criterion"; and
"In the UK NRPB (1986) criteria, factors of between 1 and 15 are used,
depending on the individual risk"
Section 25.8.5 of that document gives a number of examples of expenditure on
RRMs and concludes that there is general agreement that the PF should range
between 1 and 10.
è
This paragraph is being withheld under Exemption 13 of the Code of
Practice on Access to Government Information (commercially confidential
information).
ç
A1.4 NORSOK Standard
The NORSOK Standard Z-013 ("Risk and Emergency Preparedness Analysis)
includes an annex discussing cost benefit analysis. Section E5.2 of this annex
includes information on the valuation of benefits to personnel and the cost of
an improvement to Norwegian helicopter based SAR preparedness. These values can
be use to derive an implied PF of approximately 2.5. Generally, PFs up to
approximately 15 might be justified.
A2.1 Introduction
CBA is a technique that provides data to be used in the judgement on whether
cost of risk reduction is gross disproportionate or not. It is a judgement
and other factors are involved, particularly whether the outcome is so severe
that measures are needed to address societal concern (Principles and Guidelines
document, paragraphs 34 and 35).
The ratio of costs/benefits (known as the proportion factor) is
sensitive to the event frequency, which may be uncertain by an order of
magnitude or more. There is therefore little point in expending significant
effort over choosing the discount rate or quantifying a value for the remaining
life of the plant, as we shall later.
This Annex outlines a simplified approach to CBA that will enable inspectors
to take account of the proportion factor and weigh it against risk when judging
whether a measure is reasonable practicable or not. If the decision is finely
balanced the duty holder should be asked to present more detailed analysis –
including a sensitivity analysis. Such requirements are likely to be infrequent.
A2.2 Simple CBA
One way of estimating the proportion factor is to ‘annualise’ the costs
and benefits. Suppose a risk reduction measure is equivalent to an annualised
cost of £10k per year, and the benefits are equivalent to 0.01 lives saved per
year. The cost of preventing a fatality, CPF (see R2P2) is the ratio of
these quantities i.e. 10,000/0.01 i.e. £1M. Since HSE generally adopts £1M as
the value of preventing a fatality there is no disproportion between the costs
and benefits. Since the disproportion must always be gross the measure must
be implemented.
A2.2.1 Estimating the annualised costs
First consider the Table below which shows the factor to annualise the
cost, C, of a risk reduction measure, when adopting different discount rates
(DR) and plant life times. The figures in brackets represent normalised values
with respect to a period of 15 year and a DR of 6%. The deviations from the
normalising value (0.103) are less than a factor of two; the extremes (0.149 and
0.058) are less than a factor of 3 apart – which is ‘small’, compared with
other uncertainties.
|
Plant life, yrs
|
DR = 4%
|
DR = 6%
|
DR = 8%
|
|
10
|
(1.2)
|
0.136 (1.3)
|
0.149 (1.4)
|
|
15
|
0.090 (0.9)
|
0.103 (1)
|
0.117 (1.1)
|
|
20
|
0.074 (0.07)
|
0.087 (0.08)
|
0.102 (1)
|
|
30
|
0.058 (0.05)
|
0.073 (0.07)
|
0.089 (0.08)
|
Suppose a measure costs £1M and implementation leads to production losses of
£15k. However, the duty holder will be able to reduce running costs (lower
maintenance costs etc.) by £5k per year for about 25 years – the estimated
life of the plant. This ‘benefit’ has to be offset against the costs – see
R2P2. Thus for a DR of 6% the annualised costs, based on the annualisation
factor of (0.087+0.073)/2 = 0.08 are:
|
a) annualised cost of measure (see above table) |
0.08 x £1M = 80,000 |
|
b) loss of production |
0.08 x £15k = 1,200 |
|
c) reduced operating costs etc.- for simplicity ignore
discounting |
= -5,000 |
|
Net annualised costs |
= 76,200 |
A2.2.2 Estimating the annualised benefits
Before implementation the incident probability is 10-5 per year
and results in an average of 8 fatalities. After implementation the
corresponding figures are 10-6 per yr. and 2. The damage and clean-up
costs would be around £25M before implementation and around £10M after
implementation. This is approximately equal to a further 25 and 10 lives
respectively, taking the value of preventing a fatality, VPF of £1M. So we are
saving the equivalent of (25 + 8)x10-5 – (10 + 2)x 10-6
lives per year i.e. (33 – 1.2)x 10-5 = 31.8x10-5 lives
per year.
So the approximate cost of preventing a fatality, CPF is £76,200/31.8x10-5
i.e. ca £240M. The proportion factor = CPF/VPF = 240, which is clearly
disproportionate.
This example is based on one submitted by a duty holder. They used a DR of 6%
for costs and 4% for benefits, and a VPF of 1.65M and other details. Using their
VPF, the CPF becomes 76,200/(23.1-0.8)x10-5 i.e. £341.7M, so the
proportion factor is 341.7/1.65 = 207. This is, given the uncertainties, very
close to the gross disproportion factor estimated by the duty holder i.e. 174.
For the purposes of making a judgement the figures are identical.
One further simplification that can be adopted is to, initially, assume that
all harms are averted (and hence not have to spend time doing the ‘situation
after’ assessment). If the measure is not reasonably practicable on this basis
it is not reasonably practicable at all and can be screened out. If it is
marginal or appears reasonably practicable then the ‘situation after’ can be
assessed and the analysis refined. Alternatively, a duty holder may just choose
to implement the measure for the avoidance of doubt and with a view to spending
money on measures rather than analysis to show whether a measure is or is not
strictly required.
A2.3 Sensitivity analysis
For the example above, suppose the failure rates and estimates of fatalities
are optimistic by a factor of 10. Our estimate of equivalent fatalities (VPF=£1M)
is (25+80)x10-4 – (10+20)x10-5 = 102x10-4. So
the CPF = £76.2k/0.01 = £7.62M The proportion factor is therefore 7.62.
Whether this is grossly disproportionate would depend how realistic the casualty
count is, on who was killed (vulnerable populations, etc) and how as these
parameters affect societal risk. If 80 people die, the decision will probably
hinge on the societal risk issue, and whether scale aversion was factored [5]
into the decision on disproportion.
If the revised estimates were judged to be realistic, there would clearly be
a need for more detailed analysis and discussions between the HID team and the
duty holder before a decision on gross disproportion could be made. But given
that the disproportion must always be gross, very convincing arguments from the
duty holder would be needed. Tools like ARIcomah may need to be used
with an appropriate aversion index and more detailed CBA to get a better
estimate of the proportion factor when aversion is considered.
A2.4 Conclusions
A simple approach to CBA has been presented that only requires a hand
calculator. It does not give any credit for scale aversion, which could increase
the proportion factor that would be regarded as gross. It is recommend to HID as
a quick way of screening out measures that are not reasonably practicable.
Careful consideration of what is a cost and what is a benefit is needed.
When decisions fall into a grey area and there is appreciable societal risk,
ARIcomah could be used to assess the influence of scale aversion on
the proportion factor and aid the judgement on gross disproportion.
--------------------------------------------------------------------------------
[1] See I.L. Hirst and D.A. Carter A "worst
case" methodology for obtaining a rough but rapid indication of the
societal risk from a major accident hazard installation, Journal of Hazardous
Materials, Volume 92, Issue 3, 10th June 2002, pages 223-237
This is based on F-N societal risk plots having a slope of –1, which is
supported by past incident experience.
[2]It might be impractical to ask Duty Holders to perform case specific
demonstrations for all identified events immediately. A more pragmatic option
would be to insist that the "representative set "or "safety
critical events" are considered now with the remaining risk generators
being subject to scrutiny in a rolling program, leading up to the time of the
next safety report submission.
[3]Mark Middleton & Andy Franks "Using Risk Matrices", The
Chemical Engineer, September 2001, pp. 34 – 37
[4] The full methodology is described in the paper by Hirst and Carter (see
footnote 1 for full reference).
[5] See Hirst and Carter paper (see footnote 1 for full reference).
This guidance is issued by the Health and Safety
Executive. Following the guidance is not compulsory and you are free
to take other action. But if you do follow the guidance you will
normally be doing enough to comply with the law. Health and safety
inspectors seek to secure compliance with the law and may refer to this
guidance as illustrating good practice.
back to top