Major incident investigation report
BP Grangemouth Scotland : 29th May - 10th June 2000
A Public report prepared by the HSE on behalf
of the Competent Authority
The incidents
Fluidised Catalytic Cracker Unit (FCCU) Fire - 10th June 2000
The Competent Authority investigation
required that BP should take the following measures before re-introduction
of hydrocarbon to the FCCU “light ends” section. The incident has
substantial commercial implications for the site. (The Fluidised Catalytic
Cracker Unit is currently not operational whilst BP are evaluating the
option of re-building the facility).
FCCU
Recommendations – Prior to restart
Mechanical
integrity
Demonstration that the mechanical integrity
of pipework on the “light ends” section of the FCCU is assured, in
particular, with respect to the following:
-
Stresses
caused by:
-
Fabrication;
- Assembly
and erection, including misalignment and structural attachments;
- Mechanically
induced vibration cycling;
- Temperature
effects and thermal cycling;
-
Self
weight and effect of supports, restraints and guides;
- Reaction
forces and other shock loading;
-
Pressure;
-
Erosion,
corrosion and environmental cracking.
- Dead legs and
drain points to be minimised and, where retained, assessed against the
above failure modes.
- Redundant
equipment and pipework, including drain/vent points, to be removed,
where practicable.
BP confirmed that the
recommendations would be addressed before the FCCU was started up again
and would be dealt with in the design of the revamped “light ends”
section.
Emergency
shutdown arrangements
Demonstration that adequate arrangements
have been identified for the emergency shutdown of the “light ends”
section of the FCCU need to be considered (in particular the following):
- Installation
of remotely operated shut-off valves (ROSOVs) to allow rapid remote
isolation of significant process inventories in order to minimise the
consequences of an uncontrolled leak and allow remote emergency
shutdown of ancillary equipment, such as pumps.
- Safe means
for emergency depressurisation of columns or vessels, where reasonably
practicable.
BP confirmed that the
recommendations would be addressed before the FCCU was started up again
and would be dealt with in the design of the revamped “light ends”
section.
Alarm flooding
Demonstration that adequate arrangements
have been identified to ensure a timely and effective response by Central
Control Building operators to those alarms necessary for the prevention
and mitigation of major accidents, taking due account of the number,
presentation and rate of presentation of alarms during plant start up, or
other upset conditions, and any relevant factors set out in industry best
practice guidelines (the EEMUA
guidelines).
BP confirmed that the
recommendations would be addressed before the FCCU was started up again
and would be dealt with in the design of the revamped “light ends”
section.
Further FCCU
recommendations
The HSE investigation also recommended
that improvements be made in the following areas of FCCU operation.
- Change
control – rigorous change control procedures should be employed;
- Risk
assessment – a review of the FCCU risk assessment should be
undertaken which considers critical process effects on start-up, e.g.
de-watering, opening FCVs, exceeding process parameters, thermal
cycling, transmitted vibration etc;
- Control/instrumentation/electrical
equipment;
- Management
review – a high level overview of unit operations should be
maintained to ensure abnormal operation of the process plant is
identified and the full implications assessed;
-
Communications/competency
– process technicians should receive additional training and
instructions to enable them to recognise situations where there may be
serious implications for process plant.
Recommendations
for the Complex
The HSE investigation also recommended that
improvements be made in the following areas site wide.
- Pipework
inspection regime – a review of the corporate inspection regime
should be carried out in the light of the FCCU history and other
refinery incidents;
- Redundant
equipment – a policy should be put in place for redundant equipment;
- Remote
isolation of process plant – BP’s philosophy on remote isolation
of plant should be reviewed. The implications for other plants on the
Complex should be considered;
- Project
review – the corporate system for reviewing the effect of
significant projects (PHSER Stage 6) should be followed;
- Process
safety review – systematic reviews should be initiated at regular
intervals to help assure the overall integrity of process units. They
should include the following elements:
-
Operating
and inspection histories;
- The
validity of previous risk assessments;
- Hardware
and software changes;
-
Significant
incidents and near misses;
- Audits;
- Measurement
against current standards and legislation;
- Major
accident hazards identified in safety reports.