Major incident investigation report
BP Grangemouth Scotland : 29th May - 10th June 2000
A Public report prepared by the HSE on behalf
of the Competent Authority
The incidents
Fluidised Catalytic Cracker Unit (FCCU) Fire - 10th June 2000
-
The primary
immediate cause of the FCCU incident was the fracture of an
unsupported 6x3” reducing tee branch pipe to the main transfer line
between the Debutaniser column (E5) and the Re-run column (E6) due to
fatigue failure. This resulted in the release of highly flammable
liquid/vapour at elevated temperature and pressure, which subsequently
ignited.
- It was
fortunate that no fatal or serious injury occurred to the four or five
workplace members in the immediate vicinity. This was due to a
combination of the way the fire started and progressed, and the
workers positioning at the time of the incident and presence of mind
to move to safe positions. Weather conditions assisted and the vapour
did not accumulate in and around the buildings or in the plant. Under
different circumstances this could have led to a vapour cloud
explosion, (a scenario envisaged in the CIMAH safety report), which
would have increased the likelihood of fatal injuries and further
escalation of the incident.
- There were
serious operational problems associated with the FCCU stage two
modifications in 1997/98 which were a relevant underlying cause of the
major accident on 10th June. These were inadequately
dealt with by BP despite recommendations in writing from the HSE to
review the process after the torch oil explosion late in 1999.
- BP reviewed
the FCCU earlier in 2000, partly to try to determine why it was not
operating properly (eventually traced to a blocked cyclone dip leg)
and to compare it with BP FCCU world standards. The review findings
were not implemented or communicated properly.
The findings of the Competent Authority
investigation in relation to the five themes identified earlier are given
below.
Legislative
Compliance
This was a major accident as defined under
the COMAH Regulations that could have
resulted in multiple fatalities under different circumstances. It was
identified that there were a series of deficiencies which resulted in BP
being prosecuted under the Health and Safety at Work Act 1974.
Best Practice/Guidance
Comparison of the organisational set-up
with the “POPMAR” safety management system model in HSE Booklet HSG65
“Successful Health and Safety Management” suggested major
weaknesses in failing to organise to meet the high standards required in
the Major Accident Prevention Policy (required by COMAH) and in planning
and implementing and in monitoring, audit and review. Underlying problems
were identified in the following areas:
- Organisational
structure – the HSE accept that these were historic and had been
identified by BP who were taking steps to address the issue when the
incidents occurred;
-
Operational
review system;
- Maintenance
of integrity of pipework to avoid loss of containment scenarios;
- Risk
assessment procedures;
- Consideration
of Human Factors issues.
BP Grangemouth Safety Reports
The CIMAH FCCU installation safety report
1997/98 revision claims and concludes that – “hardware and software
controls in place on the FCCU are adequate to prevent the occurrence of a
major accident which could affect the general public, the personnel
working on-site or the environment around it.” Based on investigation
findings, this was partly unjustified even in 1997 when it was submitted,
and certainly did not reflect the reality by 10th June 2000
when the cumulative effects of unreliability, numerous plant start-ups,
vibration and unsupported pipework factors came together. The safety
report was not proactively used as a management standard for reviewing
continued safe operation, nor used as an audit tool to verify the claims
made for safe operation. There were serious deficiencies in the COMAH
compliance regime and the safety report did not reflect the reality of the
plant operations and maintenance.
BP Group objectives
BP failed to fully meet their own high
performance standards in “Getting HSE
Right (GHSER)”.
Previous Incidents/Recent History of
Operation
Between spring 1998 and June 2000 there was
an increased number of start ups and shut downs on the Vapour Recovery
Unit. Further, a number of incidents had occurred over the previous
two years in which vibration was a relevant issue. A summary list of these
previous incidents is given below:
- 1998 - Two
incidents occurred which involved vibration of the transfer line
between E5/E6. The problem was resolved by adjusting the flow between
the columns;
- March 1999 -
Vibration of the transfer line between E5/E6 caused failure at a
screwed connection for a flow transmitter impulse line. The impulse
line was repaired and back-welded. The origin of the vibration was not
ascertained;
- December 1999
- On starting up the “light ends” section, a leak was noted at a
vent stub on a slurry circuit common header. This header was linked to
circulation pumps and contained hot slurry i.e. hydrocarbons at or
above their auto-ignition temperature. The cause of failure was
attributed to transmitted vibration due to cavitation from the pumps.
This vent stub had not been used since the header was installed two
years previously and the line was unsupported 1” carbon steel piping
with two manual valves attached;
- May 2000 - A
plant operator noted significant vibration, or shock-loading, of the
transfer line E5/E6 on two occasions. Both occurred shortly after
start-up. The information was not passed onto the BP’s Asset
Technical Support or BP’s Plant Integrity Branch;
- May 2000 - A
plant operator noted violent movement of the slurry return circuit
shortly after start-up. This is located adjacent to the E5 column. The
line contains hydrocarbons above the auto-ignition temperature. The
information was not passed onto the relevant persons;
- May 2000 –
Leak of propane from a screwed coupling on a 1” drain line on the
Depropaniser overheads line. The screwed plug leaked due to
transmitted vibration when a high pressure in E7 during start-up
caused relief valves on the column to lift. The
drain line was only supported at the welded joint to the overhead
line. At the time of the release, the drain line was at a pressure of
approximately 23 barg and there was no means of isolating this section
of line. Operator’s by-passed the E7 column to prevent further
inventory from entering the column, but could do little other than
wait for the line to depressurise (over two hours). Light winds at the
time meant that propane gas did not accumulate on the plant and no
ignition resulted. The cause of failure i.e. vibration due to a
process upset and RV’s lifted, was not passed onto BP’s Plant
Integrity Branch.
In addition to the incidents identified
above there had been another incident in November 1999 when a prolonged
start-up attempt on the FCCU resulted in an ignition of a torch oil vapour
cloud within the ductwork of the CO boiler. Contrary to plant operating
instructions in the master operating manual (1997), the torch oil had been
admitted to the Regenerator when the unit was at too low a temperature. As
a result ignition of the torch oil did not occur in the Regenerator.
Although ignition had not been verified, a considerable further quantity
of torch oil was injected and it is believed that hot spots in the slumped
catalyst bed vapourised the torch oil. The provision of a temperature
interlock had previously been considered and discounted, as it was decided
that operating procedures alone were a sufficient control.
As a result of the torch oil incident the
HSE issued an improvement notice to BP requiring an abnormal operations
risk assessment procedure to be developed and recommended review of the
operation of the FCCU to be undertaken. BP complied with the terms of the
improvement notice.