HSE banner

Health & Safety Executive / Local Authorities Enforcement Liaison Committee (HELA) HELA
LACORS
PETEL

  • Subject: Autogas
  • LAC Number: 65/60
  • Open Government Status: Fully Open
  • Keywords: Petrol filling stations, autogas installations, and LPG
  • Issued: September 2005
  • Review date: September 2008

To: All Unitary and Island Councils; County Councils and Fire and Rescue Authorities in England

For the attention of: Environmental Services / Trading Standards / Fire Authorities

This circular gives advice to Petroleum Enforcement Officers


The dangerous substances & explosive atmospheres regulations 2002
Petrol filling stations - Autogus installations

Inspector’s Aid Memoir Check List

Explanatory Notes

1. Initial and periodic surveys of autogas installations (at petrol filling stations) by Fire Safety Officers and LA Inspectors can only, for practical reasons, encompass the following features:

NB:

Certain parts of the installation may be inaccessible when unannounced inspections are carried out, as the site operator may not hold the keys to dispenser and access chamber covers.

At sites where the storage vessels are buried/mounded, other than the dispenser(s), there will be little to inspect.

2. Under the Dangerous Substances & Explosive Atmospheres Regulations 2002 (DSEAR)a the site operator has the responsibility for the operation of the installation, including the maintenance even other duty holders may carry out the maintenance work.  For example on some sites it is not unusual for there to be other duty holders involved by virtue of the storage vessels and the installation being owned by separate companies. 

3. The Written Scheme of Examination required under the Pressure Systems Safety Regulations 2002 (PSSR)b is very specific and Section 8 requires that ‘The Written Scheme’ must cover the periodic examination of:

NB:

The term “danger” in the context of PSSR applies only to the release of pressure;

The Written Scheme may or may not be held by the site.

4. PSSR, DSEAR and Provision & Use of Work Equipment Regulations 1998 (PUWER)c require that maintenance be carried out. This may be carried out independently from or as part of the work required by the ‘Written Scheme’.  As the operator is responsible to ensure this work is carried out, then there should be suitable records available.  If they are not kept on site then they should be readily available from a specified location; e.g. a head office. 

5. Liquefied Petroleum Gas Association (LPGA) Code of Practice (CoP) 20 includes recommendations for the maintenance of Autogas installations on which the notes in following table are based.  The Code also recommends that the site operator should be carrying out routine checks of the main parts of the installation, especially those parts that could affect customer safety.  e.g. nozzle, hoses, pullaway coupling, dispenser condition and emergency shut down system.

6. The following tables also give an indication of what should be included in the installation checks carried out by the site operator or specialist contractors.

Electrical Installationd    

No.

Item

Notes

1

Electrical inspection schedule and/or maintenance records available.

See LPGA CoP 1 & 20 and Blue Book

Mechanical Installation
The maintenance record should include the following information. It may be possible for some of the information to be verified by an inspector during a visit.
Storage Vessel Compounds    

No.

Item

Notes

2

Storage type

Above ground/Mounded/Buried

3

Chamber gas sensors

Confirm installed (for buried installations only).  Although not mandatory, sensors are installed at many sites.

4

Means of escape from vessel compounde.

Two outward opening, lockable, gates on opposite sides of the compound.  See LPGA CoP 1 (para 2.6.1)

5

Condition of compound and base including security fencing and any radiation wall(s).

Fence and/or radiation wall to be no closer than 1.5m.

6

Vessel surroundings clear of flammable materials and excessive vegetation.

 

7

Condition of paint/external surface protection of vessels.

Confirm no significant external corrosion started

8

Presence and legibility of signs on vessel/compound

Should be clearly legible when viewed from the limits of the relevant separation distance.

9

Emergency telephone number displayed and is correct

Required by emergency services.

Should be clearly legible when viewed from the limits of the relevant separation distance.

10

Condition of all valves, pipework and fittings

Confirm no evidence of damage or severe corrosion.  Moderate surface corrosion may be expected on some fittings and earth bonding points without impacting on overall integrity.

11

Condition of pump(s) and motors

Confirm no damage or severe corrosion

12

Emergency (pump) isolation switch(s) installed in the compound.

Fitted with a suitable sign

For use by the tanker driver or engineer working in the compound.

Pipework & Ducting    

No.

Item

Notes

13

Condition of flexible (under dispenser) pipe

Confirm no evidence of mechanical damage.  See PETEL 65/54a.  Check there are no leaks mechanical damage or corrosion.

14

Buried pipework – inspection strategy.

Confirm that there is a strategy in place that covers the buried/concealed pipework with the necessary checks and tests to establish continued integrity, the intervals between checks/tests and the rationale supporting the strategy.  See LAC No 52/18

15

Condition of seals in ducting.

Effectively sealed with mechanical or compound seals. See PETEL 65/54a. Builders (PE) expanding foam not sufficient on it’s own

16

Location of buried pipework

Should be marked on the forecourt or shown on a site plan available to contractors and the emergency services.

Dispensers    
No. Item Notes

17

Shear couplings

Visual survey to confirm brackets are in place and secure.  Check the thinned section to confirm no cracking

18

Dispenser hoses

Hoses should receive daily visual check (by the site operator) and an annual leak test at operational pressure

19

Pullaway

Many manufacturers recommend testing every 6 months. The period between testing should not exceed 12 months.

20

Nozzles (general)

Nozzles should receive daily visual check (by the site operator).  In addition they must be checked by a competent person for correct and safe operation at least once every 12 months. Replace nozzle if any evidence of mechanical damage or leaking during normal operation.
The manufacturer of Gasguard nozzles recommends a nozzle is replaced after 24 months service for new or reconditioned unit. (Reconditioned nozzles should be to the latest factory standard.).

21

Nozzle adaptors

Does the site operator have a policy on the use of adaptors?

22

Emergency isolation valves (ROSOVs)

The system should be checked at least once a year to confirm correct operation.

23

Signs on dispenser

Warning signs plus instructions on how to use the type of nozzle fitted.

Fire Precautions    
No. Item Notes

24

Separation distances being maintained between autogas installation and other site features.

See LPGA CoP 20

25

Hazardous area classification

See LPGA CoP 1 & 20, Section 3 Blue Book (2nd edition) and DSEAR

26

Water supplye

See LPGA CoP 1

27

Fire extinguisherse

See LPGA CoP 20 & Blue Book  (2nd edition).

Documentation    
No. Item Notess

28

Instructions for operations, maintenance and emergencies

DSEAR, PUWER, LPGA Codes of Practice.
Include results of previous surveys and schedule for checking underground pipework

29

Installation details and test certificates.

Test certificates may be held elsewhere especially if the vessels are owned by another organisation.

30

Hazardous area classification

See LPGA CoP 1 & 20, Section 3 Blue Book and
DSEAR

31

Records of staff training

Relevant staff should have received training on the hazards, safe handling and emergency procedures for LPG.

32

Incident reporting

Are records kept or reporting procedures for any leaks of LPG or incidents of customers or staff receiving cold burns.

Enforcement Allocation at a Petrol Filling Station  

Legislation

Enforcing Authority

DSEARa

PLA

PSSRb

LA (Environmental Health Dept)

PUWERc

LA (Environmental Health Dept)

Electricity at Work Regulations 1989d

LA (Environmental Health Dept)

Fire Precautions (Workplace) Regulations 1997e

Fire & Rescue Service

HSWA

LA (Environmental Health Dept)

Appendix

Schedule for Equipment Maintenance.      

Equipment

Annually2

Every 5 Years2

Every 10 Years2

Base and steelwork

Visual

   

Vessel*1

Visual

 

Test

Vessel signs1

Visual

   

Vessel fittings*1: -

fill

liquid out

liquid return

vapour return

relief valve*

pressure gauge

drain

Test

Test

Test

Test

Visual

Visual

Visual

-

-

-

-

Change - if mild steel springs

-

-

Change

Change

Change

Change

Change

Change

-

Filter

 

Test

Change

Pump4

Internal bypass valve

External bypass valve

Test

Test

Test

-

-

-

Change

Change

Change

Hydrostatic relief valve*

Visual

-

Change

Test point valves

Test

Change

ROSOVs

Test

   

Dispenser: -

filter

measure

overall

Test 5-

Test option4

Visual

-

-

-

-

-

Hoses6

Test

Change

-

Pull-away coupling

Test

-

-

Safe-break coupling

Visual

-

-

Nozzle

Test

Change

-

Underground pipework

See item number 14 in check list.

   

Notes:

Those items marked * should be included in the “Written Scheme of Examination”. (WSE)

1Vessel maintenance is often carried out by the gas supplier. Some suppliers have a 20 year period between major overhauls.

2For guidance only, the intervals for each installation should be specified by the competent person drawing-up the Written Scheme of Examination and maintenance schedules

3Vessel signs should be changed if they are faded and/or cannot be read from the separation distance.

4The periods between pump and/or bypass valve changes will depend on the performance of the installation

5The periods between cleaning/changing depend on the performance of the dispenser and the type of filter.

6The BS for hoses requires a test at periods not exceeding 12 months for hoses >25mm inside diameter.  Most autogas installations will have hoses with internal diameters of <25mm.

Procedures for testing for measure should take into account typical volumes dispensed and the flow rate applicable for the installation under normal conditions.

ROSOV: Remote Operated Shut-Off valves (Emergency Shutdown valves.)