Distribution Networks Operators’ Approved Replacement Programmes 2011 - 2012

1. Under the Pipelines Safety Regulations 1996, regulation 13A [90KB] ,   HSE approves the iron mains replacement programmes submitted by the gas Distribution Network Operators (DNOs). 

2. The approved targets for the period 1 April 2011 to 31 March 2012 are shown in Table 1.

3. The overall national target for the period 1 is 3690.4 km.

Table 1 – Approved mains replacement programmes 2011 – 2012 by Distribution Network

Network Distribution Network operator Decommissioning
Target (km)
North West National Grid Gas plc 521.0 1820.0
East of England 599.0
West Midlands 340.0
North London 360.0
North of England Northern Gas Networks Limited 528.1
Scotland Scotland Gas Networks plc 269.0*
South of England Southern Gas Networks plc 712.3*
Wales & West Wales & West Utilities Limited 361.0*
All networks 3690.4

4. Normally HSE approves iron mains replacement targets annually. However, HSE will approve programmes lasting more than one year if:

  • the DNOs are able to demonstrate that equivalent or higher length of mains and amounts of risk will be removed, and
  • the DNOs set annual targets within the longer programme.

5. In Table 1 targets marked with an asterisk (*) form part of 3-year approved programmes from 1 April 2010 to 31 March 2013.

6. As part of its monitoring strategy and 5 year intervention plans for the DNOs, HSE will carry out mains replacement audits to check that mains are decommissioned in accordance with the policies and procedures in the DNOs’ Gas Safety (Management) Regulations 1996 safety cases.